German company wpd plans to repower one more of its wind farms in Croatia. The Orlice wind farm will not only have more powerful wind turbines, but also a 10 MW battery energy storage system.
Wpd earlier initiated the procedure to repower its Trtar-Krtolin wind farm (11.2 MW), the second-oldest wind power plant in Croatia. In addition, the company has announced plans to convert the Katuni wind farm into a hybrid power plant by adding a solar park.
Wpd is one of the pioneers in renewable energy in Croatia.
The Orlice wind farm was commissioned in 2009 as the third wind power plant in the country. It comprises 11 Enercon wind turbines with a total installed capacity of 9.6 MW. It is located on the territory of the city of Šibenik, within Šibenik-Knin county.
Repowered plant to feature three wind turbines
The company plans to dismantle and remove the existing 11 wind turbines and install three new units with an individual capacity of 6 MW. Three new foundations will be constructed for the new turbines at the locations of the existing foundations.
The planned total installed capacity of the wind farm upon repowering would reach up to 20 MW, according to the environmental protection study for the repowering project.
The investor plans to revegetate, with indigenous flora, approximately 1,500 meters of access roads that will no longer be in use.
Wpd’s newest wind farm was commissioned in 2017
The environmental protection study was submitted by the company Vjetroelektrana Orlice to the Ministry of Environmental Protection and Green Transition alongside a request for an environmental impact assessment (EIA) screening for the repowering of the Orlice wind farm.
In Croatia, wpd also operates the Ponikve wind farm on the Pelješac peninsula. It is its largest one, at 38.6 MW.
Wpd’s most recently commissioned facility is the 34.2 MW Katuni wind farm, which came online in 2017.