Preparations are underway for repowering the Trtar-Krtolin wind farm, which was commissioned in 2006 near Šibenik. Croatia’s first wind power plant – Ravne 1 (5.95 MW) – began producing electricity two years earlier.
After 20 years of operation, the Trtar-Krtolin wind farm in Croatia is entering reconstruction, and the comparison of technical details demonstrates how much wind energy technology has advanced during that period.
The plant, built by Germany’s wpd, consists of 14 Enercon E-48 wind turbines with an individual capacity of 800 kW, mounted on 50-meter-high towers, with a rotor diameter of 48 meters. The total installed capacity is 11.2 MW.
The battery’s role would be to optimize the wind farm’s production
The makeover of the Trtar-Krtolin wind farm involves the replacement of the 14 existing wind turbines with no more than five new ones, of up to 6 MW each, according to the environmental impact report for the Trtar-Krtolin wind farm repowering project.
The request for the assessment was submitted to the Ministry of Environmental Protection and Green Transition by Vjetroelektrana Trtar Krtolin, registered in Dubrovnik.
The investor also plans to install a battery energy storage system (BESS) of up to 10 MW and 20 MWh.
The battery would be used for the optimization of the wind farm’s production, namely storing energy from production when the plant is operating at full generating capacity, and delivering it to the grid when production within the electricity system is insufficient and the timing is most favorable, the report reads.
Extension of operational lifespan
The investor explained that the project’s objective is to repower the wind farm to allow for the extension of its operational lifespan, enabling energy generation in a safe, economically viable, and environmentally friendly manner, and the delivery of electricity into the Croatian power system.
In line with the European Union’s directives on repowering renewable electricity plants, the EIA is limited to potential effects arising from changes or expansion versus the original project, the investor noted.
Of note, wpd said in mid-2023 that it planned to build a solar power plant at the site of its existing wind farm Katuni in Croatia.