Greece’s efforts to establish electricity interconnections between the Dodecanese and North Aegean islands with the mainland grid have moved forward in recent weeks.

Projects for the two large electricity interconnections have a combined budget of about EUR 4.5 billion, based on the latest recalculation, carried out this year by the Independent Power Transmission Operator (IPTO or ADMIE) under its new ten-year development plan. Links with the Cyclades islands and two with Crete have been completed

Manousakis: Greece has a modern power system thanks to European support

Last week, the European Commission said it was awarding a EUR 228.9 million grant for the Dodecanese line via the Public Sector Loan Facility (PSLF), with further EUR 1.53 billion as a loan coming from the European Investment Bank (EIB). The endeavor also benefits from a EUR 534 million grant from Greece’s Decarbonization Fund, for a total of EUR 2.54 billion in public or European support.

Recently, IPTO’s Chairman and CEO Manos Manousakis highlighted that 30-35% of the operator’s overall capital expenditure comes from European funds. “Without European support, we would not have the electric system we have today in Greece,” he acknowledged.

Seabed surveys and cable production secured

IPTO has already prepared to commence seabed surveys along the route to Dodecanese, through the selection of specialized vessels. Relevant clearances were provided from Greek authorities for the ships.

French company Nexans was selected as a subcontractor to produce the cables. According to its statement, their length will reach 1,260 kilometers, making this one of the most ambitious high-voltage direct current (HVDC) projects in the wider Mediterranean. Cable construction is expected to take place from late this year to the middle of 2028.

A Greek company, Asso.subsea, will handle the laying of the cables upon the route.

Goal is to reduce high power production costs

IPTO’s Vice Chairman Ioannis Margaris said recently that electricity production in the islands of Dodecanese and Northern Aegean costs about EUR 1 billion per year. It is particularly expensive. The cost from the utilization of the oil-fired power plants is shouldered by every consumer in the country.

The new connections will provide much cheaper electricity from the mainland, leading to the decommissioning of those local stations, or to keep them as a reserve. They are expected to reduce the overall power system cost in the country, as well as electricity bills. Last but not least, they will allow further development of renewable energy and storage in the islands.