E.ON completes EUR 8 million investment in energy supply security

Published

March 20, 2015

Country

Comments

comments icon

0

Share

Published:

March 20, 2015

Country:

Comments:

comments icon

0

Share

Modernization and Scada system integration of E.ON Moldova Distribuţie S. A. substations’ project was completed by E.ON Distribuţie România, Germany’s biggest power supplier’s subsidiary based in Târgu-Mureș, Business-review.eu portal said.

The project was co-financed by the European Regional Development Fund (FEDR), following a RON 35 million (EUR 8 million) investment. The project was implemented over a period of 32 months starting with July 25, 2012, in 26 substations.

Tags:

Related Articles

bih croatia south interconnection pipeline intergovernmental agreement three seas kristo plenkovic

BiH, Croatia sign agreement on Southern Gas Interconnection

29 April 2026 - Bosnia and Herzegovina and Croatia have signed an intergovernmental agreement on the construction of the Southern Gas Interconnection

croatia grid connection fee hera decision

Croatia finally sets grid connection fee

29 April 2026 - The Croatian Energy Regulatory Agency (HERA) has adopted the fee for the connection to the electricity network

TerraPower Natrium Rendering nuclear power plant

TerraPower starts building 345 MW nuclear plant in US using advanced Natrium technology

29 April 2026 - The facility is set to become “the first utility-scale advanced nuclear power plant in the United States,” TerraPower said

Aktor LNG USA signs 20 year supply deal with Albania's Albgaz

Aktor LNG USA signs 20-year supply deal with Albania’s Albgaz

29 April 2026 - Aktor LNG USA and ALBGAZ signed a 20-year commercial agreement for liquefied natural gas (LNG) from the United States