Albania has 570 MW of solar projects in pipeline

Albania has 660 mW of solar projects in the pipeline

Photo: joseluisv from Pixabay

Published

January 17, 2022

Country

Comments

comments icon

0

Share

Published:

January 17, 2022

Country:

Comments:

comments icon

0

Share

Private and state-owned companies are advancing in the licensing procedure for the installation of six large and ten small solar power plants. Most are planned to be built in Fier county. Projects with a combined 570 megawatts (MW) have achieved progress in the past two years, compared to the existing 23 MW in the entire country.

The photovoltaic projects are in the various stages of the licensing procedure conducted by the Energy Regulatory Authority (ERE), the Ministry of Infrastructure and Energy, and the National Environmental Agency (AKM).

ERE said it has started the procedure for granting licenses to developers SVP Blue 1 and SVP Blue 2 for their two planned solar power plants, each with 50 MW. The same process was initiated for state-owned power utility KESH’s 5.1 MW facility at the dam of its Vau i Dejës hydropower plant, but it is said to have already completed it. The company is also preparing to install a 12.9 MW floating photovoltaic unit at the same reservoir.

The procedures are handled by regulatory body ERE, environment agency AKM, and the relevant ministry

The same procedure has been launched for a 140 MW photovoltaic project under development by Karavasta Solar.

Another project in Fier county is for Info-Telecom’s 50 MW solar park. The company has just applied to the National Environmental Agency to obtain environmental permits, which would allow it to continue its development.

The proceedings in ERE and in AKM are for more advanced endeavors than the ones handled by the ministry.

The latest big project, of 150 MW, was launched by Aga-Solar – it is the largest one in the pipeline so far

Last month, the ministry said that it received an application for a 150 MW power plant from Aga-Solar. The company intends to build the facility in Fier county. Additional nine applications for the construction of PV facilities, each under 2 MW, have recently been submitted to the ministry.

There is one other utility-scale project in Albania for the 100 MW Spitalle solar park. French company Voltalia won it in an auction after coming in on top in the bidding for Karavasta as well.

In August, Prime Minister Edi Rama claimed that Albania would become a regional champion in renewable energy production by 2030.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Montenegro EPCG trial run of first wind park Gvozd

Montenegro’s EPCG starts trial run of its first wind park – Gvozd

10 May 2026 - EPCG launched the trial operation of its first wind power plant. Gvozd would be the biggest in Montenegro when the second phase is completed.

Hellenic Hydrogen wins European Hydrogen Bank grant with lowest bid

Hellenic Hydrogen wins European Hydrogen Bank grant with lowest bid

08 May 2026 - The European Hydrogen Bank (EHB) approved EUR 1.09 billion in the third auction. A Greek JV won with the lowest bid in the general category.

croatia cropex koer ante mikulic ceo

CROPEX CEO leaves power exchange to join aggregator KOER

08 May 2026 - A similar move – transitioning from a high-ranking position in the public sector to a private company – recently took place in Slovenia as well

electricity meter ppc energie romania zero cost

PPC Energie rolls out Romania’s first zero-cost electricity scheme

08 May 2026 - Power supplier PPC Energie has launched a pilot project offering free electricity during certain hours of the day to customers with smart meters