Bulgaria reluctant to join regional auction platform

Published

May 14, 2015

Country

Comments

comments icon

0

Share

Published:

May 14, 2015

Country:

Comments:

comments icon

0

Share

Plans to create a single European cross-border capacity auction platform is holding back the Bulgarian transmission system operator from joining the regional platform. This is despite the fact a joint European auction platform might only be operational by 2019, petrochemical market information provider ICIS reported.

At a recent industry event, Victoria Popovska, head of the electricity market department at Bulgarian grid operator ESO, said it was not planning to join the recently established coordinated auction office SEE CAO, but instead waiting for the new joint EU auction office JAO.

Miloš Mladenović, corporate director for international and regulatory affairs at Serbian grid operator EMS, said that the company had started discussions with SEE CAO. EMS could use the auction platform for some of its borders before it joins JAO.

SEE CAO had faced numerous delays before it launched in the end of last year.

The grid operators of Croatia, Bosnia and Herzegovina, Kosovo*, Greece, Turkey, Montenegro and Albania are shareholders, but it currently only holds daily and monthly auctions for the borders between Croatia, Bosnia and Herzegovina, Albania and Montenegro.

The participation of the Bulgarian and Serbian operators was considered crucial and they together with Macedonia were potentially facing dispute procedures if they failed to comply.

In the end of March, a representative of the Energy Community told ICIS that the organisation expects Serbia to participate in the 2016 coordinated yearly capacity auctions for the Southeast European markets.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.

Related Articles

eu western balkans cbam electricity market amendments

EU’s amendments to CBAM: possibility of relief, but January 1 brought market uncertainty

06 January 2026 - Long-awaited implementing acts and amendments to the CBAM Regulation brought only a minor relief for...

After adding PV unit Slovenian gas power plant TEB battery project

After adding PV unit, Slovenian gas power plant TEB launches battery project

06 January 2026 - The management of the Brestanica gas power plant has decided to diversify its activities further with a battery energy storage system

D Trading offtake 200 MW solar PPA with Econergy Romania

D.Trading to offtake 200 MW of solar in PPA with Econergy in Romania

06 January 2026 - DTEK Group's D.Trading signed an offtake deal with Econergy for 200 MW of solar power in Romania, including the country's largest PV plant

montenegro TSO cges investments ranko redzic

Montenegro’s TSO CGES to invest EUR 200 million

05 January 2026 - Montenegrin TSO CGES plans to invest EUR 200 million, according to Ranko Redžić, manager of the company's national dispatching center