Environment

Serbia rejects Zijin’s request to separate environmental assessments in copper smelter project

Serbia Zijin s separate environmental assessments copper smelter

Photo: Curioso Photography on Unsplash

Published

March 15, 2021

Country

Comments

comments icon

0

Share

Published:

March 15, 2021

Country:

Comments:

comments icon

0

Share

The Ministry of Environmental Protection instructed Zijin to produce an environmental impact assessment study for the entire copper smelter expansion project in Bor, denying the company’s request to exclude preparatory construction works. RERI highlights the high risk from the investment and points out that separating such endeavors into smaller units would hide cumulative damage.

Based on objections from the Association of Young Researchers Bor and the Renewables and Environmental Regulatory Institute (RERI), the Ministry of Environmental Protection of Serbia rejected the request by company Serbia Zijin Copper to decide on the need for an environmental impact assessment for a part of its project and ordered it to conduct a study for the entire complex.

The two organizations have been raising the alarm in the public and with the ministry, arguing that the attempt is a case of salami slicing – artificial fragmentation of a project to hide the impact on the environment. Zijin wrote to the ministry in December with a claim that a study for the preparatory construction works within the expansion of its copper smelter in Bor isn’t necessary. They include excavation and the enlargement and reconstruction of existing structures.

Ministry changes course

Legal expert from RERI Hristina Vojvodić pointed out that the Chinese company already tried to break up the projects for increasing its output into smaller pieces and that the latest decision is “unique and made from a completely opposite standpoint” than in similar processes in Serbia lately.

RERI is looking into information that some of the planned structures have already been built

She told Balkan Green Energy News it is the first time that an investor is trying to exclude preparatory works and said that the organization is looking into information that some of the planned structures have already been built.

“The construction permit can only be issued after the impact assessment study is approved. The project includes a desulfurization unit and a sulfuric acid plant and storage facility, making it potentially very dangerous for the environment. If Zijin obtained the permits, it would get the right to launch construction even though it wouldn’t know if it would be allowed to implement the entire endeavor. The ministry instructed the company that it can’t divide the project and it was a necessary move to get the whole picture,” Vojvodić stated.

Preparatory construction works have no independent purpose

According to the Law on Planning and Construction, the construction of a structure consists of preliminary works, the production and supervision of technical documentation, preparatory construction works, the construction itself and simultaneous professional oversight. It means that the aforementioned works aren’t a separate project and that they have no independent purpose, RERI said.

There is an increasing number of attempts by companies to copy or imitate the methods with which other investors managed to hide the environmental impact of large projects

When the construction of the smelter in Serbia’s east is viewed as a whole, the negative environmental impact and the necessity of a study become obvious, the experts and activists said.

Hristina Vojvodić stressed the responsibility of state institutions and highlighted the attempts by investors to “copy, imitate the methods” that worked for other investors. On the other hand, citizens and activists now pay more attention and the public is interested in the information on infringements, she underscored.

Typical examples of salami slicing were registered in projects for Linglong’s tire factory in Zrenjanin and coal-fired thermal power plant Kostolac B3, Vojvodić said.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Rumen Radev Minister of Energy Iva Petrova Bulgaria

Rumen Radev’s cabinet including Minister of Energy Iva Petrova takes office in Bulgaria

08 May 2026 - Prime Minister Rumen Radev's cabinet took office today. New Minister of Energy Iva Petrova comes from the position of deputy minister.

srbija hibridi benzinci kriza

Hybrid vehicles overtake petrol cars on Serbian market

30 April 2026 - Sales of new hybrid vehicles in Serbia in the first quarter of the year surpassed those of petrol cars, according to the latest data

Croatia investments EU ETS proceeds EUR 650 million

Croatia proposes investments from EU ETS proceeds of EUR 650 million

28 April 2026 - Within the framework of EU ETS, Croatia is counting on EUR 650 million through 2030 from auctions of greenhouse gas emission allowances

europe electric vehicles cars iran war crisis

Iran war boosts sales of electric vehicles in Europe – 51% growth

23 April 2026 - Data published by New Automotive and E-Mobility Europe reveals that over 224,000 new electric passenger cars were registered in March alone