Government and A2A agree to prolong partnership

Published

October 15, 2015

Comments

comments icon

0

Share

Published:

October 15, 2015

Comments:

comments icon

0

Share

Minister of Economy Vladimir Kavarić said the Government of Montenegro and Italian-based company A2A have reached an agreement on the basic elements of future cooperation and the extension of cooperation for five years once the shareholders’ agreement in the Electric Power Industry of Montenegro (EPCG) gets signed towards the end of the year. Meanwhile, the interim agreement, which was extended at a cabinet session by endorsing the interim agreement annex, will be in force, he said at a press conference.

Both sides agreed on the obligations, dynamics, and financial framework for the construction of the block 2 of the Thermal Power Plant Pljevlja. Kavarić added that the drafting of a business plan has also been arranged, which will be a backbone for measuring the EPCG’s future performance.

The Economy Minister pointed out that the Government and A2A have also agreed on a put option for A2A’s investment worth EUR 430 million at the time of entering the EPCG in 2009. A2A is eligible to initiate this option in certain specific circumstances, and in that case Montenegro would be ready to pay EUR 250 million in seven annual instalments for the A2A shares in the EPCG, Minister Kavarić noted.

The deadline for agreement officially expired earlier this year, and it was postponed four times.

Related Articles

Greenvolt GE Vernova wind turbines 250 MW project in Romania

Greenvolt orders GE Vernova wind turbines for its 250 MW project in Romania

05 December 2025 - GE Vernova said it would start delivering 42 wind turbines next year to Greenvolt Power for the Gurbănești project near Bucharest

More than 330,000 Europeans died due to air pollution in 2023

More than 330,000 Europeans died due to air pollution in 2023

05 December 2025 - The EEA has determined that in 2023 there were 333,000 cases of premature death linked to exposure to particulate matter, ozone and nitrogen dioxide.

Wpd obtains wind power approvals in Greece for 225 MW

Wpd obtains wind power approvals in Greece for 225 MW

04 December 2025 - Wpd has won environmental approvals for a wind power project of 147.6 MW in Central Greece and one for 77 MW in Thrace

bih serbia elnos Sinohydro powerchina vetrozelena wind farm contract

Elnos to construct grid connection for wind farm Vetrozelena in Serbia

04 December 2025 - Vetrozelena, with its planned 300 MW, is the largest wind power plant under construction in Serbia