EPBIH ready to continue construction of Tuzla 7 coal project

EPBIH ready to continue construction of Tuzla 7 coal project

TPP Tuzla (photo: EPBiH)

Published

September 13, 2021

Comments

comments icon

0

Share

Published:

September 13, 2021

Comments:

comments icon

0

Share

Elektroprivreda Bosne i Hercegovine (EPBiH) is willing to continue the construction of unit 7 in the Tuzla thermal power plant because the project has no alternative, according to the company’s representatives. The Chinese partners in the EUR 700 million project expressed a similar stance, announcing readiness to finish the project.

The Tuzla 7 coal project, planned as a unit to replace the existing aging units 3, 4, i 5, has been stalled for almost a year after General Electric decided not to supply the equipment. In October last year, GE informed the main contractors, Gezhouba Group and the Guangdong Electric Power Design Institute from China, that it could not supply the boiler, turbine and steam-turbine generator because it was withdrawing from coal-related business.

The Tuzla 7 project was halted by GE’s exit from coal-related operations

The two companies informed EPBiH, which then told the authorities of the Federation of BiH about the situation, but to date no solution has been found. The Chinese companies have also proposed the missing equipment, based on Siemens technology, to be delivered by Shanghai Boiler Works Co. in cooperation with GE and Shanghai Electric Group (SEC). The Chinese have also tried to hire European companies, but most, like GE, are withdrawing from the coal sector.

Andelija: Propose another solution and the company will accept it

EPBiH General Manager Admir Andelija has now told local media that the company has no alternative but to continue building Tuzla 7.

He called on all those who are against the project to find another solution and said the company would accept it.

EPBiH wants to continue the implementation of the construction contract, which it has upheld so far, Andelija said and invited the Chinese partners to continue cooperation.

Chinese contractors hope their alternative proposal to continue construction would be accepted

Izet Žigić, President of the Supervisory Board of EPBiH, told BHRT television the utility doesn’t accept any alteration with regard to the agreed technology. Only the Government of FBiH and the federal parliament can approve changes, he added.

Gezhouba Group and Guangdong Electric Power Design Institute said they understand the importance of the project for the economy and energy security of BiH, just like EPBiH, and that they hope the main equipment would soon be available.

They stressed that they hope EPBiH and the FBiH authorities would accept the alternative proposal so that the construction of unit 7 can start as soon as possible.

We are wasting money at a facility that will be closed in about 15 years – Denis Žiško

Environmental organizations have a completely different view of the situation. Denis Žiško from the Center for Ecology and Energy said  it makes no sense to invest millions in a power plant that would be closed in fifteen years, arguing the upcoming CO2 tax would make it unprofitable.

The CO2 tax will make the project unprofitable

Unit 7 would reduce emissions of sulfur dioxide and particulate matter, but the problem with large amounts of slag and ash would remain, he said, as quoted by Klix.ba.

EPBiH does not plan to modernize anything, but to continue disposing of slag and ash containing heavy metals, dangerous for the population, according to Žiško.

He proposed to direct investments into renewable energy sources, energy efficiency and smart grids. For example, to secure subsidies for households to install solar panels on their roofs.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia trans balkan corridor ems kodar contract bajina basta obrenovac matejic

Serbia’s TSO EMS inks contract for Obrenovac – Bajina Bašta power line within Trans-Balkan Corridor

18 March 2025 - Serbia’s transmission system operator Elektromreža Srbije signed a contract for the construction of a two-system 400 kV transmission line

PPC construction 165 MW solar farm BESS Bulgaria

PPC begins construction of 165 MW solar farm with BESS in Bulgaria

18 March 2025 - PPC Group is accelerating its expansion in the Balkans by laying the foundation stone for its Colosseum solar power project in Bulgaria

montenegro new law on energy sahmanovic

Montenegro adopts new energy law

17 March 2025 - A new Law on Energy will allow citizens to become active participants in the electricity market in Montenegro

north macedonia kontek asi trade solar probistip

Turkey’s Kontek to take over solar project in North Macedonia

17 March 2025 - Kontek plans to acquire an 85% stake in Asi Trade-M, the company developing the 111 MW solar power project