GEEN Holding AS has said it formally launched its second combined heat and power (CHP) plant in Croatia. The biomass unit in Županja has the capacity of 4.9 MW for electricity and it is equivalent to the Benkovac project, finished last year. The heating portion comes in at 8.5 MW and a maximum of 10 MW.

The value of the investment is CZK 1 billion (EUR 39.2 million) and the company based in Brno, Czech Republic, revealed it expects to return it in five years. The third such plant in the country will be in Gospić, according to previous plans.

After completing the trial period, output started at a rate of 40 GWh of power per year. Woodchips and pellets are used in the turnkey endeavor, which includes a drier for the fuel. The projected consumption of biomass is 55,000 tons per annum, translating to 33,000 tons of carbon dioxide less than with conventional sources, GEEN claimed in documents.

Earlier reports indicated ten to 15 people may work at the facility. Also before, a subcontractor said the capacity for electricity generation would be 5.8 MW in total of which 4.96 MW would be eligible for incentives and that the difference would be used for own consumption.

The main contractor is Đuro Đaković Termoenergetska postrojenja Doo (ĐĐ TEP) from nearby Slavonski Brod. Biomass to Energy Županja Doo, registered in Vrbovsko, is running the CHP plant.

The Benkovac unit is designed for 41 GWh of output. The investor developed a similar blueprint for Gospić, a town in the central part of the Balkan country. Works are scheduled to be finished next year. Total expenditure on the three projects is EUR 120 million.

Croatia is incentivizing CHP or cogeneration technology as part of the strategy to lift the share of renewable sources in gross final energy consumption to 36.4%. The first domestic geothermal plant was inaugurated last month. It has a binary or ORC system.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia auctions regulations quota wind solar

Serbia proposes regulations for its second round of wind, solar auctions

22 October 2024 - The Ministry of Mining and Energy issued, for public consultation, the draft decrees on an upcoming round of auctions for premiums

UGT Renewables UGTR Hyundai Engineering US Serbian solar battery Adam Cortese interview

UGT Renewables, Hyundai Engineering opening new era in US-Serbian relations with giant solar-battery project

22 October 2024 - UGT Renewables and Hyundai Engineering are at the forefront of the US-Serbia energy cooperation agreement, UGTR's CEO Adam Cortese said

Final Greek NECP changes goals for renewable energy, pumped hydro and hydrogen

Greece adjusts goals for renewables, pumped hydropower, hydrogen in final NECP

21 October 2024 - After a lot of back and forth during the last several months, Greece has presented its final version of the NECP

iea energy security electricity

IEA warns geopolitical tensions pose risk for energy security, urges faster clean energy transition

18 October 2024 - Demand for fossil fuels is expected to peak by the end of the decade, as the world is moving fast towards the "age of electricity"