Electricity

Romanian journalists uncover giant hybrid power plant project on Serbian border

Romanian journalists uncover giant hybrid power plant project Serbian border

Photo: International Hydropower Association / https://creativecommons.org/licenses/by/2.0/legalcode

Published

March 30, 2023

Country

,

Comments

comments icon

0

Share

Published:

March 30, 2023

Country:

,

Comments:

comments icon

0

Share

A dormant wind, solar and pumped hydropower project valued at EUR 1.9 billion has been unearthed by Economica.net. The complex was supposed to be built on the Danube on Romania’s border with Serbia.

A huge planned investment in the energy sector in Romania has never been publicly discussed, Economica.net reported. Its reporters saw that the country’s transmission system operator Transelectrica deleted a pumped storage hydropower project of no less than 1 GW from its website. It turned out that there is a blueprint for a renewable energy complex of a whopping 2.42 GW.

The site is in Caraș-Severin county in the country’s west, on the border with Serbia. It would span 1,080 hectares on the territory of the Socol commune, which would approve a concession. A local urban planning document was also supposed to be produced.

According to a presentation from 2019 obtained by the news outlet, the renewable electricity production complex was supposed to include a 920 MW wind farm and a photovoltaic unit of 500 MW.

The pumped storage unit was valued at just EUR 300 million in a presentation from 2019, against EUR 1.1 billion for the wind park

The 1 GW pumped storage hydropower facility was envisaged to optimize output and provide balancing services to the national electricity system. It would have an upper reservoir of 18 million cubic meters and use the reservoir of the Iron Gate 1 hydropower plant on the Danube. Romania shares the hydroelectric plant with Serbia. It is called Porțile de Fier 1 in Romanian and Đerdap 1 in Serbian.

The hybrid power plant project was valued at almost EUR 1.9 billion at the time. The idea was to connect it by overhead or underground lines to the interconnector stretching from Reșița in Romania to Pančevo in Serbia, the article adds. The line is part of the Trans-Balkan Electricity Corridor.

Annual output was estimated at 2.6 TWh, with carbon dioxide emission savings of 920,000 tons.

The company that launched the project has said it would connect the hybrid power plant in Socol to the Reșița-Pančevo interconnector

The cost of the pumped storage plant, which was planned to work in production and pumping cycles of six to eight hours, was estimated at EUR 300 million. It compares to EUR 1.1 billion for the wind farm, EUR 400 million for the photovoltaic park and EUR 84 million for the high-voltage line.

The project was launched by MOE-HPG Timișoara, registered in Socol, until delisting at the end of 2021, the report reveals. Its representatives told the Ministry of Energy in 2019 that they counted on investment funds, a loan from the European Investment Bank, grants from the European Union, financing from a sovereign investment fund that was planned at the time and potential funds from support schemes for the reduction of CO2 emissions.

In the past several months, Romanian companies revived a string of abandoned hydropower projects.

Of note, Serbia is developing a project for pumped storage hydropower plant Đerdap 3 on the border with Romania.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Greece DEPA Commercial financing 816 MW solar power portfolio

Greece’s DEPA Commercial obtains financing for 816 MW solar power portfolio

26 July 2024 - State-controlled DEPA Commercial received a EUR 390 million loan from the EIB for photovoltaic projects across Greece

serbia energy cooperative solar power plant elektropionir

First cooperative solar power plants in Serbia start production

26 July 2024 - The income from the sale of electricity will be used for projects proposed by the communities of the villages on the Stara planina mountain

faria renewables mykonos solar power plant

Faria Renewables acquires 35 MW Mykonos solar project

26 July 2024 - Faria Renewables S.A. has announced the integration of photovoltaic project Mykonos into its asset portfolio

Ameresco Sunel Energy 560 MW solar power Greece Lightsource bp

Ameresco Sunel Energy starts building 560 MW solar power plant in Greece for Lightsource bp

26 July 2024 - Ameresco Sunel Energy is the contractor in Lightsource bp's solar power project of 560 MW in peak capacity, in the central part of Greece