Renewables

BiH to add 116 MW with two wind farms – Grebak, Vlašić

bih wind farms vlasic grebak

Photo: bastiarius from Pixabay

Published

November 30, 2020

Comments

0

Share

Published:

November 30, 2020

Comments:

0

Share

The preparations for the construction of the first wind farm in the Republic of Srpska – Grebak (66 MW) are over, and negotiations on financing the construction of the Vlašić wind farm (50 MW) in the Federation of Bosnia and Herzegovina are starting.

Wind farms Grebak and Vlašić, with a total capacity of 116 MW, should be built within four years in Bosnia and Herzegovina. So far, the country has two wind farms: Mesihovina (50.6 MW) and Jelovača (36 MW), which means the total would reach at least 202.6 MW.

At the same time, the grid is ready to handle as much as 1,700 MW in additional capacity.

Grebak wind farm project capacity increased by 16 MW

An annex to the concession agreement for the construction of the Grebak wind farm was signed in order to increase the installed capacity from 50 MW to 66 MW. According to the Ministry of Mining and Energy of the Republic of Srpska, works will begin this week.

Minister of Energy and Mining Petar Đokić and Miralem Čampara, CEO of VE Grebak, a company based in Nevesinje, BiH, sighed the document. The investment is estimated at EUR 66.1 million.

The turbine technology has advanced since the start of the concession procedure, and their installed capacity has been increased, so there is a possibility to increase the capacity of the entire wind farm, the ministry said.

Negotiations with the EIB on a loan for Vlašić are starting

The Federation of BiH is making progress on its way to get another wind farm. It is a project of state-owned power utility Elektroprivreda Bosne i Hercegovine (EPBiH), which a few weeks ago received approval to finance the investment with loans.

At the proposal of the Ministry of Finance and Treasury of BiH, the country’s Council of Ministers appointed a delegation to negotiate a financing agreement between BiH and the European Investment Bank (EIB) for the construction of the Vlašić wind farm.

Green light to start talks on a EUR 36 million loan

The EUR 36 million loan will be approved to the Federation of BiH as the borrower, with a repayment period of 20 years and a deferment for the first four years.

The project is planned to be implemented by 2024. It envisages the construction of a wind farm on the Vlašić plateau which will produce electricity for the domestic power system, according to a press release of the Council of Ministers of BiH.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

western-balkan-power-utilties-decarbonization-plans

Decarbonizing Western Balkan power utilities: ambitious but flexible plans, with focus on investments and new technologies

17 May 2024 - Power utilities in the Western Balkans have ambitious goals for 2050, but are flexible in mapping the path because the development of technologies is unpredictable

Banks Serbia receiving lot requests grid connection guarantees Belgrade Energy Forum

Banks in Serbia receiving lot of requests for grid connection guarantees

17 May 2024 - Banks in Serbia are receiving numerous requests for guarantees for renewables requiring grid connection and most investors have firm collateral instruments, according to speakers at Belgrade Energy Forum

statkraft neoen croatia Arnaud Bellange Christophe Desplats-Redier

Statkraft acquires Neoen’s project portfolio in Croatia

17 May 2024 - According to Arnaud Bellanger, Country Manager for Croatia and France at Statkraft, the takeover deal covers about ten projects

Turkey adds 1 3 GW solar power capacity April alone

Turkey adds 1.3 GW in solar power capacity in April alone

17 May 2024 - Photovoltaic capacity in Turkey reached 13.9 GW by the end of last month or a stunning 1.3 GW more than on March 31