ESM halts investment in Belene project, turns to gas power plant near Alexandroupolis LNG terminal

esm belene lng alexandroupolis

Photo: Max Mustermann from Pixabay

Published

November 27, 2020

Country

Comments

comments icon

0

Share

Published:

November 27, 2020

Country:

Comments:

comments icon

0

Share

State-owned energy company Elektrani na Severna Makedonija (ESM) suspended investments in Bulgaria’s nuclear power plant Belene, and shifted its focus to the construction of a gas power plant near the planned liquefied natural gas (LNG) terminal in Alexandroupolis in Greece.

ESM estimates the LNG terminal and 800 MW gas project would be finished earlier than the construction of Belene, pointing to the significance of securing a stable supply of gas to customers in North Macedonia, local media reported.

ESM believes the gas-fired power plant would be built before the Belene nuclear power plant

Issues arose in the supply of electricity a few months ago in North Macedonia. The energy system is in a very delicate situation.

ESM said the LNG terminal and gas power plant have better chances to be finished sooner than the Bulgarian nuclear power plant.

North Macedonia plans to phase out coal, and is turning to renewables and natural gas

ESM officially sent a letter of intent last year to acquire a minority stake in the Belene project, which was abandoned in 2012 and revived in 2018. This year North Macedonia has also received an offer from Greece to participate in the development of the Alexandroupolis LNG terminal and own 25% of the 800 MW gas power plant or 200 MW.

North Macedonia’s interest in the two projects is related to the country’s strategy to phase out coal and move to renewables and natural gasEnvironmental protection and sustainable development are among the six main tasks for the four-year mandate of Prime Minister Zoran Zaev’s recently elected cabinet.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Uncompetitiveness holds EU far behind green hydrogen targets

Uncompetitiveness holding EU far behind green hydrogen targets

05 December 2025 - Several high-profile renewable hydrogen projects have been cancelled and major companies have reduced their decarbonization ambitions, ACER said

Greenvolt GE Vernova wind turbines 250 MW project in Romania

Greenvolt orders GE Vernova wind turbines for its 250 MW project in Romania

05 December 2025 - GE Vernova said it would start delivering 42 wind turbines next year to Greenvolt Power for the Gurbănești project near Bucharest

Wpd obtains wind power approvals in Greece for 225 MW

Wpd obtains wind power approvals in Greece for 225 MW

04 December 2025 - Wpd has won environmental approvals for a wind power project of 147.6 MW in Central Greece and one for 77 MW in Thrace

bih serbia elnos Sinohydro powerchina vetrozelena wind farm contract

Elnos to construct grid connection for wind farm Vetrozelena in Serbia

04 December 2025 - Vetrozelena, with its planned 300 MW, is the largest wind power plant under construction in Serbia