State-owned energy company Elektrani na Severna Makedonija (ESM) suspended investments in Bulgaria’s nuclear power plant Belene, and shifted its focus to the construction of a gas power plant near the planned liquefied natural gas (LNG) terminal in Alexandroupolis in Greece.

ESM estimates the LNG terminal and 800 MW gas project would be finished earlier than the construction of Belene, pointing to the significance of securing a stable supply of gas to customers in North Macedonia, local media reported.

ESM believes the gas-fired power plant would be built before the Belene nuclear power plant

Issues arose in the supply of electricity a few months ago in North Macedonia. The energy system is in a very delicate situation.

ESM said the LNG terminal and gas power plant have better chances to be finished sooner than the Bulgarian nuclear power plant.

North Macedonia plans to phase out coal, and is turning to renewables and natural gas

ESM officially sent a letter of intent last year to acquire a minority stake in the Belene project, which was abandoned in 2012 and revived in 2018. This year North Macedonia has also received an offer from Greece to participate in the development of the Alexandroupolis LNG terminal and own 25% of the 800 MW gas power plant or 200 MW.

North Macedonia’s interest in the two projects is related to the country’s strategy to phase out coal and move to renewables and natural gasEnvironmental protection and sustainable development are among the six main tasks for the four-year mandate of Prime Minister Zoran Zaev’s recently elected cabinet.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Bistrica study pumped storage eps

Serbia moves closer to building Bistrica pumped storage hydropower plant

24 April 2026 - The construction of Bistrica will provide 55 GWh of energy storage capacity and enable the integration of 1.5 GW of renewables

serbia region eu energy community mou balkan green energy news lorkowski jovicic

Energy Community Secretariat, Balkan Green Energy News sign MoU to advance clean energy awareness across Balkans

24 April 2026 - The MoU outlines the framework for collaboration, ensuring accurate, timely, and balanced reporting while upholding the media's independence

bih republic of srpska dso elektrokrajina distribution grid loan ebrd

BiH’s DSO Elektrokrajina to invest EUR 30 million in distribution grid

24 April 2026 - The Council of Ministers of BiH has approved an initiative to begin negotiations for a loan aimed at upgrading the distribution grid

Serbia’s TSO EMS inks deal to invest EUR 36 million in substations

24 April 2026 - Works on substations in Bajina Bašta and Obrenovac are part of the third section of the Trans-Balkan Corridor for electricity transmission