Bulgaria, Croatia, Romania, Slovenia plan to burn coal beyond 2030 – report on final NECPs

Bulgaria,-Croatia,-Romania,-Slovenia plan-to-burn-coal-beyond-2030-report-on-final-NECP

Photo: Pixabay

Published

June 5, 2020

Country

Comments

comments icon

0

Share

Published:

June 5, 2020

Country:

Comments:

comments icon

0

Share

A new report published by Climate Action Network (CAN) Europe and ZERO looks into the final national energy and climate plans (NECPs) of 15 member states including countries in Southeastern Europe – Croatia, Greece, Romania, and Slovenia.

In their initial drafts, a number of countries had already put forward much needed coal phaseout goals in the power sector by 2030 at the latest.

Seven member states however plan to burn coal beyond 2030: Bulgaria, Czechia, Germany, Romania, Poland, Croatia, and Slovenia, the report finds.

Improvements cannot catalyze the energy transition required to achieve the long term objective of the Paris Agreement

For each country, the report Pave the Way for Increased Climate Ambition: Opportunities and gaps in the final National Energy and Climate Plans brings a comparison between the draft and final NECP, and displays opportunities and gaps.

A number of countries made some improvements, however, it is not enough to catalyze the energy transition required to achieve the long term objective of the Paris Agreement, CAN Europe said on its website.

The European Commission is expected to present its assessment on the final NECPs

In the following months, the European Commission is expected to present its assessment on the final documents.

NECPs are a vital part of the Clean Energy For All European Package, adopted by the European Commission in order to achieve three basic targets for 2030.

Croatia: No measures to reduce the use of coal by 2030

For Croatia, the final NECP does not envisage measures to reduce the use of coal by 2030, although the country’s energy strategy does not include electricity generation from coal power plants after 2035. The two plans have to be harmonized, taking into account measures for a coal phaseout, which should be referenced in the NECP even if it is intended to phase out coal only after 2030.

Romania: Risk of locking in gas infrastructure

Romania plans to keep almost 2 GW of installed coal capacity at least until 2030 and to use natural gas to a considerable extent as “a transition fuel” to a decarbonized energy industry, which creates the risk of locking in gas infrastructure.

Slovenia: Use of coal for electricity production until 2050

Slovenia foresees the use of coal for electricity production until 2050 and considers investments in carbon capture and storage (CCS) technology. It foresees the gradual phasing out of domestic and imported coal for energy purposes with a view to reducing it by at least 30% by 2030. Instead of setting a clear deadline for closing coal-fired power plants, Slovenia will make a decision regarding phasing out coal only in 2021.

Greece: Big increase in fossil gas capacity

Although Greece’s final NECP includes the decision to shut down existing lignite coal plants by 2023 and fully phase out lignite by 2028, the electricity that was supposed to be produced by lignite in 2030 is substituted mostly by fossil gas and, to a much lower extent, by renewables and energy storage. Therefore, the final NECP includes a big increase in fossil gas capacity compared to the draft. Out of the 9.1 ΤWh of lignite-based electricity that will be phased out, 8 TWh will be replaced by fossil gas.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Project 81 MW solar park on coal mine in Montenegro

Project underway for 81 MW solar park on coal mine in Montenegro

24 July 2025 - The Government of Montenegro gave a provisional green light for a solar power plant of 81.1 MW in peak capacity on coal land in Pljevlja

croatia rp global novalja solar ebrd loan

RP Global gets EUR 12.2 million loan for Novalja solar project

24 July 2025 - In late April, Austrian company RP Global began the construction of the Novalja PV plant at the Zaglava site on the island of Pag

solarpower europe report 2025

EU faces first annual solar installation decline since 2015 – report

24 July 2025 - The EU is set to install less new solar in 2025 than it did in 2024 - the first annual drop in a decade, according to SolarPower Europe

Faria Renewables secures financing 49 9 MW battery project Greece

Faria Renewables secures financing for 49.9 MW battery project in Greece

24 July 2025 - Faria Renewables has signed a loan agreement with Attica Bank for the construction of a BESS facility in Greece