Electricity

Nexans to begin laying cable to Syros under Aegean Sea

undersea cable

Photo: ADMIE

Published

December 5, 2019

Country

Comments

comments icon

0

Share

Published:

December 5, 2019

Country:

Comments:

comments icon

0

Share

Top officials from the Independent Power Transmission Operator SA (IPTO or ADMIE) of Greece and contractor Nexans SA, based in France, announced yesterday in Lavrion port that boats are about to start rolling out the electric cable in the third phase of establishing an interconnection with Cyclades Islands.

The first, 28-kilometre section of the submarine link will be laid in a matter of days, the state-owned firm added and noted the plan is to finish the remaining 80 kilometres in the first quarter and reach the island of Syros. ADMIE claimed the cable project, which is being launched southeast of Athens, would be completed in a year.

The 150-kV HVAC (high-voltage, alternating current) submarine interconnection will be the second one, doubling the transmission capacity, according to the statement. Greece’s transmission system operator or TSO said the new infrastructure under the Aegean Sea would prop up supply and push down the prices of electricity.

interconnection link

The EUR 111 million cable to Syros, Paros, Naxos and Mykonos will ease the utilisation of renewable energy sources, according to the firm. Works on the link are cofinanced by the European Union and the government.

Τhe phase C of the Cyclades electrical interconnection, which has already been accelerated by two years, will safeguard the supply and provide backup for a planned or sudden shutdown, according to ADMIE’s chairman and chief executive.

Two 328-kilometre HVDC (high voltage, direct current) cables are planned to be installed under the Sea of Crete and the Myrtoan Sea to connect the Balkan country’s biggest island also with Attica peninsula, where the capital city is situated. A EUR 365 million link from Crete and the southeastern tip of the Peloponnese peninsula is set to come online next year.

China has expressed interest in purchasing a 20% stake in ADMIE’s subsidiary running Ariadne, the first of the two international endeavors. The deadline for it is 2023.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

eu smart meters acer list slovenia croatia

Slovenia tops EU list for most smart power meters, Croatia among laggards

25 July 2025 - At the top of the list of European Union member states with the highest number of smart meters are the Scandinavian countries and Italy

serbia wind farm plandiste nis met dubravka djedovic

Government of Serbia interested in taking over Plandište wind project

25 July 2025 - Plandište is one of the projects that obtained feed-in tariffs under the first quota of 500 MW for wind power plants in Serbia

Project 81 MW solar park on coal mine in Montenegro

Project underway for 81 MW solar park on coal mine in Montenegro

24 July 2025 - The Government of Montenegro gave a provisional green light for a solar power plant of 81.1 MW in peak capacity on coal land in Pljevlja

croatia rp global novalja solar ebrd loan

RP Global gets EUR 12.2 million loan for Novalja solar project

24 July 2025 - In late April, Austrian company RP Global began the construction of the Novalja PV plant at the Zaglava site on the island of Pag