Final deals inked for Crete’s power link to mainland

interconnection

Photo: Pixabay

Published

November 11, 2019

Country

Comments

comments icon

0

Share

Published:

November 11, 2019

Country:

Comments:

comments icon

0

Share

A EUR 365 million undersea electric cable between Greece’s largest island and the southeastern tip of the Peloponnese peninsula is set to come online next year.

Independent Power Transmission Operator SA said the accompanying contracts for the interconnection between Crete and the mainland were signed on October 25 with Intrakat and Elektromek-Nari. The entity, which also goes by as ADMIE and IPTO, revealed the deals are worth EUR 4.5 million and EUR 5.5 million, respectively, and that they cover the construction of the Molaoi-Termatiko line and the Statcom station. In total, the two facilities are worth EUR 5.65 million and EUR 9 million, respectively.

The country’s transmission system operator (TSO) noted the agreements for the main sections of the interconnection were signed a year ago and that their implementation is underway. The government and the European Union are cofinancing the project and the European Investment Bank (EIB) provided funding.

The island’s first power link with the rest of Greece is part of the national energy plan, which foresees shutting down all power plants fueled by lignite by 2028. The EU member state aims to significantly increase the share of energy from renewable sources.

The alternating current cable is laid at depths of as much as one thousand meters. At 132 kilometres, it would be the longest in the world.

Manos Manousakis, chairman of the board and chief executive, highlighted the many years of studies and efforts leading to the realisation of the endeavour. He said the electric interconnection would strengthen the island in energy terms and ensure supply for the winter months. “With the completion of the second interconnection, Crete-Attica, the energy isolation of Crete will be completely ended and the conditions for the exploitation of the island’s renewable energy potential will be set,” ADMIE’s boss added.

The other grid system, called Ariadne, is worth EUR 1 billion. It will have two 328-kilometre high voltage direct current (HVDC) cables under the Sea of Crete and the Myrtoan Sea.

Tags:
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

heliup startup solarpower europe award stykon panels

Heliup wins European Solar Startup Award 2025 with solar panels 60% lighter than conventional ones

01 April 2025 - Heliup said it is committed to revolutionizing solar energy with lightweight solutions manufactured in Europe

Bulgaria IBEX registration market guarantees of origin electricity

Bulgaria’s IBEX opens registration for market of guarantees of origin of electricity

01 April 2025 - The Independent Bulgarian Energy Exchange (IBEX) is registering entities interested in participating in a market for guarantees of origin

hybrid solar projects LCOE batteries BESS wind solarpower europe

Hybrid solar cuts levelized cost of electricity 10% compared to standalone projects

31 March 2025 - Hybrid solar supports system flexibility, improves the cost-effectiveness of an asset, and makes energy generation more reliable

ja solar Borussia Dortmund signal iduna park

Largest solar power plant on football stadium to be installed at Signal Iduna Park

28 March 2025 - The home of Borussia Dortmund is set to become the site of the world's largest solar power plant installed on a stadium roof