Final deals inked for Crete’s power link to mainland

interconnection

Photo: Pixabay

Published

November 11, 2019

Country

Comments

comments icon

0

Share

Published:

November 11, 2019

Country:

Comments:

comments icon

0

Share

A EUR 365 million undersea electric cable between Greece’s largest island and the southeastern tip of the Peloponnese peninsula is set to come online next year.

Independent Power Transmission Operator SA said the accompanying contracts for the interconnection between Crete and the mainland were signed on October 25 with Intrakat and Elektromek-Nari. The entity, which also goes by as ADMIE and IPTO, revealed the deals are worth EUR 4.5 million and EUR 5.5 million, respectively, and that they cover the construction of the Molaoi-Termatiko line and the Statcom station. In total, the two facilities are worth EUR 5.65 million and EUR 9 million, respectively.

The country’s transmission system operator (TSO) noted the agreements for the main sections of the interconnection were signed a year ago and that their implementation is underway. The government and the European Union are cofinancing the project and the European Investment Bank (EIB) provided funding.

The island’s first power link with the rest of Greece is part of the national energy plan, which foresees shutting down all power plants fueled by lignite by 2028. The EU member state aims to significantly increase the share of energy from renewable sources.

The alternating current cable is laid at depths of as much as one thousand meters. At 132 kilometres, it would be the longest in the world.

Manos Manousakis, chairman of the board and chief executive, highlighted the many years of studies and efforts leading to the realisation of the endeavour. He said the electric interconnection would strengthen the island in energy terms and ensure supply for the winter months. “With the completion of the second interconnection, Crete-Attica, the energy isolation of Crete will be completely ended and the conditions for the exploitation of the island’s renewable energy potential will be set,” ADMIE’s boss added.

The other grid system, called Ariadne, is worth EUR 1 billion. It will have two 328-kilometre high voltage direct current (HVDC) cables under the Sea of Crete and the Myrtoan Sea.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Establishing a Robust Transmission Grid: The Essential Role of Balkan TSOs in the Green Transition

Balkan TSOs face green transition challenge: grids must keep pace with energy shift

18 May 2026 - Investments in grids, digitalization, and energy storage are key to ensuring security of electricity supply amid rapid decarbonization, representatives of regional TSOs said at Belgrade Energy Forum (BEF 2026)

serbia eu region bef 2026 energy ministers panel cooperation western balkans

Western Balkan energy ministers: Alternative supply routes, regional cooperation are key to energy security

15 May 2026 - Energy ministers from Azerbaijan, Bosnia and Herzegovina, Montenegro, North Macedonia, and Serbia met at Belgrade Energy Forum 2026

Greece Papastavrou Serbia North Macedonia join Vertical Corridor gas interconnections

Greece’s Papastavrou: Serbia, North Macedonia to join Vertical Corridor with gas interconnections

15 May 2026 - Minister of Environment and Energy of Greece Stavros Papastavrou said the Vertical Corridor would be expanded to North Macedonia and Serbia

Emblematic Ag. Dimitrios lignite plant shuts down today in Greece

Ag. Dimitrios shutdown today leaves Greece with last coal plant

15 May 2026 - Today is the last day of operation of the Agios Dimitrios thermoelectric station, Greece's largest lignite-fired facility