Final deals inked for Crete’s power link to mainland

interconnection

Photo: Pixabay

Published

November 11, 2019

Country

Comments

comments icon

0

Share

Published:

November 11, 2019

Country:

Comments:

comments icon

0

Share

A EUR 365 million undersea electric cable between Greece’s largest island and the southeastern tip of the Peloponnese peninsula is set to come online next year.

Independent Power Transmission Operator SA said the accompanying contracts for the interconnection between Crete and the mainland were signed on October 25 with Intrakat and Elektromek-Nari. The entity, which also goes by as ADMIE and IPTO, revealed the deals are worth EUR 4.5 million and EUR 5.5 million, respectively, and that they cover the construction of the Molaoi-Termatiko line and the Statcom station. In total, the two facilities are worth EUR 5.65 million and EUR 9 million, respectively.

The country’s transmission system operator (TSO) noted the agreements for the main sections of the interconnection were signed a year ago and that their implementation is underway. The government and the European Union are cofinancing the project and the European Investment Bank (EIB) provided funding.

The island’s first power link with the rest of Greece is part of the national energy plan, which foresees shutting down all power plants fueled by lignite by 2028. The EU member state aims to significantly increase the share of energy from renewable sources.

The alternating current cable is laid at depths of as much as one thousand meters. At 132 kilometres, it would be the longest in the world.

Manos Manousakis, chairman of the board and chief executive, highlighted the many years of studies and efforts leading to the realisation of the endeavour. He said the electric interconnection would strengthen the island in energy terms and ensure supply for the winter months. “With the completion of the second interconnection, Crete-Attica, the energy isolation of Crete will be completely ended and the conditions for the exploitation of the island’s renewable energy potential will be set,” ADMIE’s boss added.

The other grid system, called Ariadne, is worth EUR 1 billion. It will have two 328-kilometre high voltage direct current (HVDC) cables under the Sea of Crete and the Myrtoan Sea.

Tags:
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia hrvatska elektroprivreda hep loan goverment

Croatian power utility HEP to borrow EUR 400 million

19 December 2025 - Although the 2021-2023 global energy crisis has ended, its consequences will be felt for a long time to come

Aurora bess battery storage Bulgaria Flexible Energy Forecast service

Aurora launches Bulgaria Flexible Energy Forecast service

19 December 2025 - Aurora decided to expand its inaugural Romanian Flexible Energy Forecast service, released in April, and other established forecasts for SEE

rystad power pricing interval bess

EU’s new power pricing interval boosts BESS profit potential – analysis

19 December 2025 - Thanks to the 15-minute trading interval, arbitrage potential on the day-ahead power markets has increased by 14% on average, Rystad says

Bulgaria approves support for BESS projects totaling more than 4 GWh

Bulgaria approves RESTORE funds for over 4 GWh in BESS projects

19 December 2025 - Developers of 31 standalone battery storage facilities in Bulgaria won EUR 117 million from European Union funding