Voltalia completing its 140 MW solar power plant Karavasta in Albania

Voltalia completing 140 MW solar power plant Karavasta in Albania

Photo: Voltalia

Published

October 5, 2023

Country

Comments

comments icon

0

Share

Published:

October 5, 2023

Country:

Comments:

comments icon

0

Share

At 140 MW in peak capacity, Karavasta is the biggest photovoltaic system in the region. It is about to begin delivering electricity to the transmission system in Albania.

The largest photovoltaic facility in the Western Balkans is counting the days before the start of production. The Karavasta solar power plant will take over the title from Novaci in North Macedonia, which has just been commissioned. France-based utility Voltalia said Minister of External Trade Olivier Becht and the country’s Ambassador to Albania Catherine Suard visited the site south of Tirana.

The construction of the system with a nameplate capacity of 140 MW began 15 months ago. Notably, in April the company obtained a syndicated loan from a group led by the International Finance Corp. (IFC) and the European Bank for Reconstruction and Development (EBRD).

Investors awaiting next solar power auction

Karavasta is located in Albania’s emerging solar power hub in the Fier province, in the west. The project is valued at EUR 135 million.

Voltalia won a long-term power purchase agreement by winning a state-sponsored auction three years ago. It came out on top at the following competition as well, in 2021. The second contract is for a 100 MW solar power project called Spitalla in Durrës area, near the capital city.

Investors are expecting a public call for a 300 MW solar power auction that won’t be location-specific. Albania recently saw through the first competitive bidding procedure for wind power.

Karavasta could lose top spot in Western Balkans before too long

Hydroelectric plants still make up almost 100% of the country’s electricity production. The government is working on diversifying the mix with solar power and facilitate the construction of its first wind parks and gas-fired power plants. At least two more major photovoltaic systems are under construction in Albania.

Some of the PV projects that investors in the Western Balkans are developing are actually measured in hundreds of megawatts, though most are in the early phases. Karavasta could lose its position in the top list not before long, too. There are solar power plants under construction in Bosnia and Herzegovina and Kosovo* of 150 MW each in peak capacity.

In the wider Balkan region, the recently commissioned Kalyon Karapınar solar power plant in Turkey has a record 1.35 GW in peak capacity or 1 GW in connection terms.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Ministry of Energy and Mining of Republic of Srpska elevates cooperation with Balkan Green Energy News

Ministry of Energy and Mining of Republic of Srpska elevates cooperation with Balkan Green Energy News

16 March 2026 - The Ministry of Energy and Mining of the Republic of Srpska expanded the cooperation with Balkan Green Energy News, including the institutional partnership with Belgrade Energy Forum

Croatia HEP Group to seek contractor for wind park PV plant

Croatia’s HEP Group to seek contractor for wind park, PV plant

16 March 2026 - State-owned HEP Group is preparing a tender for a EUR 110 million investment consisting of projects for a wind park and a solar power plant

Serbia EPS gives new life to Bajina Bašta pumped storage plant

Serbia’s EPS gives new life to Bajina Bašta pumped storage plant

16 March 2026 - The EUR 35 million revitalization of the Bajina Bašta pumped storage hydropower plant in Serbia is complete

serbia edf preliminar technical study nuclear energy edf

Serbia to finalize all studies needed for nuclear program decision by mid-2027

14 March 2026 - The Ministry of Mining and Energy has organized a presentation of a preliminary technical study on the peaceful use of nuclear energy