Virtual power plants emerge in BiH as seven aggregators pool 120 MW in total

virtual power plants distributed production aggregators pandurevci nosbih

Photo: NOSBiH

Published

March 24, 2023

Comments

comments icon

1

Share

Published:

March 24, 2023

Comments:

comments icon

1

Share

Aggregation of distributed energy sources is experiencing an expansion in Bosnia and Herzegovina. Currently there are seven virtual power plants in the country, aggregating facilities with a total capacity of 120 MW, or more than all other Energy Community contracting parties combined. The Independent System Operator in Bosnia and Herzegovina (NOSBiH) foresees an increase to 250 MW by the end of the year.

Virtual power plants are also present in Croatia and Serbia. They made it possible for small producers of green energy in BiH, primarily solar power plants and hydropower plants, to sell their electricity on market at higher prices than under feed-in tariffs. It prompted their widespread exit from the schemes all over the region.

Nemanja Pandurević, general director of transmission system operator NOSBiH, noted that BiH currently has seven virtual power plants, which are also balance responsible parties, and explained electricity producers can choose how they want to sell electricity on the distribution grid level.

Pandurević: We expect virtual power plants to reach 250 MW in capacity

Speaking at the Trebinje Energy Summit – SET 2023, he said virtual power plants currently aggregate 120 MW in capacity.

He expressed optimism the trend would continue and reach maximum available capacity this year. It means all the producers connected to the distribution network, with an estimated combined capacity of 250 MW, would be aggregated.

Pandurević noted that under the feed-in tariff scheme, small power plants had to sell electricity to one of the three state-owned power companies with fixed prices via 12-15-year contracts.

The plan and realization of virtual power plants match 99%

With the energy crisis, and prices soaring in 2021, there was a need for producers to maximize profits, but there were no conditions for it, so NOSBiH, as Pandurević explained, prepared a model that enabled distributed production facilities to be aggregated. The condition for small power plants was to have an installed capacity higher than 1 MW.

Of note, NOSBiH adopted a decision in June to allow the aggregation of small power plants and their participation in the market.

Pandurević said the operator receives monthly reports from distribution system operators (DSOs) in 15-minute intervals and invoices any imbalances caused by virtual power plants.

The analysis of the deviation of the realization from the plan demonstrates that in 99% of the situations the plan is met, so NOSBiH charges small amounts for imbalance, Pandurević stressed.

Janković: It is important that the stability of the grid is not endangered

Marko Janković, electricity market chief at Serbia’s power grid operator EMS, said the focus of aggregation in BiH is on the production side.

The capacity aggregated by virtual power plants in BiH of 120 MW is, in his words, higher than in all Energy Community members put together.

He said he was satisfied to hear the concept is completely market-based and that market participants found an appropriate business model without jeopardizing the stability of the grid.

The following companies in BiH have the status of virtual power plants: EFT, Elektroprivreda BiH, Winter Wind, Hifa-oil, Renewable Energy Solutions BH, Vibar and Petrol BH Oil Company.

Comments (1)
Miodrag / March 28, 2023

Really good thing, very positive example for the region from Bosnia and Herzegovina.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Aurora forecasts Western Balkans power capacity growth 20 GW 2040

Aurora forecasts Western Balkans power capacity growth of 20 GW by 2040

15 April 2025 - The Western Balkans could see a 20 GW increase in installed capacity by 2040, with nearly 65% from renewables, Aurora Energy Research found

alcazar energy partners ifc esg summit stip wind farm north macedonia

Alcazar joins forces with IFC to develop Štip wind farm project

15 April 2025 - The start of construction of phase 1 of the EUR 500 million Štip wind farm is envisaged later this year, according to Alcazar Energy Partners

croatia Andreas Rörig e.on e-waste fee solar panels

Rörig (E.ON): Croatia charges up to six times higher e-waste fees on solar panels than other EU states

15 April 2025 - The levy slows down the use of solar energy, according to Andreas Rörig, president of the Management Board of E.ON Croatia

Upgrade prosumers to avoid grid curtailment costs up to EUR 1 000

Upgrade for prosumers to avoid grid curtailments costs up to EUR 1,000

15 April 2025 - Cyprus allowed prosumers to switch to a zero-export mode and avoid curtailments, but the cost could outweigh the benefits for most homes