Two Bulgarian coal power plants to be converted to natural gas, hydrogen

Two Bulgaria’s coal power plants to be converted to natural gas, hydrogen Varna TPP

Photo: Varna TPP

Published

June 4, 2021

Country

Comments

comments icon

0

Share

Published:

June 4, 2021

Country:

Comments:

comments icon

0

Share

The Varna thermal power plant has signed a contract to install two gas-fired combined cycle units with an installed capacity of 270 MW each, just a few weeks after the 600 MW Bobov Doal coal-fired system announced it would convert to gas and hydrogen.

Thermal power plant (TPP) Varna decommissioned three coal-fired units with an installed capacity of 630 MW in total in 2017 as it replaced them with three equivalent gas units.

Varna TPP has signed an agreement with three Russian companies for gas units

Varna TPP said it signed a contract with three Russian companies – Rakityanski Armaturny Zavod, Trubnaya Metallurgicheskaya Kompaniya and Atomenergomash, for the reconstruction of the plant using Siemens technology.

The transformation plan comprises the construction of two combined cycle power units on the site of old units 1, 2 and 3 and the ability to include hydrogen with a share of up to 30%.

The investment is estimated at EUR 450 million

Total cost of the project is estimated at EUR 450 million while the units are expected to be online in 2025, the Varna thermal power plant said.

The power utility is owned by logistics company Sigda which acquired it from Czech energy group ČEZ in 2018.

On May 20, Grand Energy Similar, owner of the Bobov Dol thermal power plant, said it would switch it to natural gas and hydrogen. The current installed capacity is 600 MW, and the new gas units are planned to be online by 2025. Bobov Dol also burns waste.

TPP Bobov Dol intends to stop burning waste

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Bulgaria boosts renewables capacity by 938 MW in 2024

Bulgaria boosts renewables capacity by 938 MW in 2024

14 January 2025 - Renewables capacity increased by 938 MW in Bulgaria last year, compared to the addition of over 1.2 GW in photovoltaics in 2023

Solarpro 174 MW solar park Romania CWP Europe

Solarpro building 174 MW solar park in Romania for CWP Europe

14 January 2025 - CWP Europe's contractor Solarpro is expected to complete a 174 MW photovoltaic facility in Romania in mid-2025

Alteo acquisitions Croatia Serbia 2 GW green platform

Alteo seeking acquisitions in Croatia, Serbia for its 2 GW green platform

14 January 2025 - Alteo, in which MOL has a minority stake, is setting off on a regional expansion, primarily in Slovakia, Croatia and Serbia

romania 2025 investments energy sector burduja

Romania to put in operation 2,500 MW of new power plants in 2025

13 January 2025 - Romania's Ministry of Energy has presented the main investments planned for 2025 in the national energy sector