Electricity

Serbia’s pumped storage hydropower plant Bistrica to cost over EUR 1 billion

bistrica japan djedovic handanovic jica imamura

Photo: Ministry of Mining and Energy

Published

January 25, 2024

Country

Comments

comments icon

0

Share

Published:

January 25, 2024

Country:

Comments:

comments icon

0

Share

Serbia has completed the feasibility study for pumped storage hydropower plant Bistrica and the cost is estimated at more than EUR 1 billion, Minister of Mining and Energy Dubravka Đedović said after speaking to Ambassador of Japan Akira Imamura about joint energy and environmental projects.

Dubravka Đedović Handanović pointed out that in the next three to four years, until the beginning of the Specialized Expo 2027 exhibition in Belgrade, the government would invest more than ever before in energy. Serbia will complete a lot of projects including a gas interconnection with North Macedonia, the Serbia-Hungary oil pipeline, Kostolac wind farm, and investments in the transmission and distribution grids, she added.

Đedović Handanović said work is underway on technical documentation for important projects, such as Bistrica and another pumped storage hydroelectric plant – Đerdap 3. She argued they would secure a more stable electricity supply and improve the balancing of the power system.

Đedović Handanović: Numerous Japanese companies are interested in the Bistrica project

Bistrica, in her view, will be a key electricity supply facility for Serbia to integrate new clean energy capacities and improve the balancing of intermittent energy sources.

This year is very important for the completion of technical documentation for the Bistrica project, Đedović Handanović underscored. The feasibility study was completed, and the total investment is estimated at more than EUR 1 billion she explained.

According to the minister, Japan International Cooperation Agency (JICA) is interested in financing, while numerous companies from Japan are willing to take part in the project’s implementation.

Imamura: Energy storage technology is very developed in Japan

Ambassador Akira Imamura expressed satisfaction that there is interest from both sides in cooperation in the construction and financing of Bistrica, but also in other energy projects. He stressed that the energy storage technology is highly developed in Japan.

Japanese companies are ready to share knowledge and experience with Serbian energy companies in building renewables, balancing and storage facilities, which is nowadays of great importance for energy systems, Imamura asserted.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Turkey's highway authority build PV plants throughout country

Turkey’s highway authority to build PV plants throughout country

26 July 2024 - After the first two, Turkey's General Directorate of Highways is installing its third solar power plant and developing three more projects

Greece DEPA Commercial financing 816 MW solar power portfolio

Greece’s DEPA Commercial obtains financing for 816 MW solar power portfolio

26 July 2024 - State-controlled DEPA Commercial received a EUR 390 million loan from the EIB for photovoltaic projects across Greece

serbia energy cooperative solar power plant elektropionir

First cooperative solar power plants in Serbia start production

26 July 2024 - The income from the sale of electricity will be used for projects proposed by the communities of the villages on the Stara planina mountain

faria renewables mykonos solar power plant

Faria Renewables acquires 35 MW Mykonos solar project

26 July 2024 - Faria Renewables S.A. has announced the integration of photovoltaic project Mykonos into its asset portfolio