Romania launches renewables auction for 3.5 GW

Romania launches renewables auction for 3 5 GW

Photo: Sebastian Burduja / Facebook

Published

May 13, 2025

Country

Comments

comments icon

0

Share

Published:

May 13, 2025

Country:

Comments:

comments icon

0

Share

Following a successful first round, in which developers won government support for projects of 1.53 GW altogether, the Romanian Ministry of Energy issued another call, for 3.47 GW of wind and solar power capacity. The deadline for submissions is July 11.

The Ministry of Energy of Romania issued a public call for the second round of auctions under a mechanism for awarding contracts for difference (CfDs). With EUR 3 billion at hand, via the European Union’s Modernisation Fund, the country is supporting an overall 5 GW of wind and solar power capacity.

Developers can apply by July 11 for the remaining quotas of 2 GW for wind parks and 1.47 GW for photovoltaic facilities. In the first round, 21 participants won the subsidies for 1.1 GW and 432 MW, respectively.

Romania cuts ceiling prices

Ceiling prices for government support are lower this time. Wind power is at EUR 80 per MWh or EUR 2 per MWh under the previous maximum possible bid. The authorities slashed the cap for solar power to EUR 73 per MWh from EUR 78 per MWh.

The contracts for difference would last 15 years. The burden of administrative and electricity transmission expenses is passed on to consumers.

More leeway for large players as they are no longer limited to 25% of quota

Another difference is that the 25% cap on the maximum capacity awarded per applicant was scrapped, the documentation shows. In addition, there is a possibility to award up to 20% more capacity than in the nominal quota. Minister of Energy Sebastian Burduja explained that the idea is to avoid the risk of losing a large project with a marginal bid.

He noted that Radramo Power is developing the largest wind power project from the first auction, 245 MW. The Heliowin project, for 125 MW, is the biggest one in the PV segment. It belongs to Israeli company Econergy. Both proposed facilities will launch production by January 28, according to the schedule.

In the first phase, applicants will qualify with their technical offers. The plan is to open financial bids from eligible entities on August 13, and the winners would have until September 9 to sign the contracts. Romania’s transmission system operator Transelectrica has the task to evaluate the applications.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

greece helleniq energy romania bulgaria wind solar profit

Bulgaria, Romania offer much higher renewable energy project returns than Greece – HELLENiQ Energy

12 August 2025 - Greece-based HELLENiQ Energy has purchased three projects at a ready-to-build phase in Romania and Bulgaria

New solar park in Romania 71 MW final permit launch

New solar park in Romania of 71 MW gets final permit for launch

12 August 2025 - Shikun and Binui Energy is about to begin delivering electricity to the Romanian grid from its Satu Mare photovoltaic plant

bulgaria batteries eso angelin tsachev

Bulgaria to add batteries of up to 10,000 MWh in capacity within months – ESO

12 August 2025 - Bulgaria’s Electricity System Operator has received grid connection applications for batteries with 12 GW in total capability

First part of Tenevo PV plant comes online batteries under construction

First part of Tenevo PV plant comes online, batteries are under construction

12 August 2025 - The largest hybrid power plant in Bulgaria is beginning to take shape as the Tenevo PV park came online and the BESS is under construction