Croatian Energy Association said it finished the ninth addition to the study on the state of renewable energy projects in the country, based on data published in early August by national energy market operator HROTE. That institution issued a document in early August, stating the 2020 quotas for wind and solar power are full, with very little capacity remaining for biogas, geothermal energy and biomass, the report said. Still, investors can add 93.68 MW more in small hydropower plants, where the quota for 2020 is 100 MW.

On August 7, there were 1,207 power plants using renewable sources that were in the system for incentives, with an overall capacity of 430,88 MW, compared to 412.59 MW from 1,070 facilities at the end of January, the report on portal Croenergo.eu added. The system has 130 new photovoltaic units, one hydropower plant, three biomass-fuelled facilities and three that run on biogas.

The 16 existing wind parks contribute to the mix with 339.25 MW, while the 1,155 solar farms have an overall 40.39 MW. The third place by capacity is now held by biogas-fired power plants, having 15.93 MW, and they overtook the rank from biomass facilities, which have 14.93 MW. The biggest individual power supplier in the segment of renewables is the 43 MW wind park of Velika glava, Bubrig and Crni vrh, operated by RP Global Danilo.

Another 138 electricity-generating facilities with 502.62 MW are in the pipeline, power purchase contracts show. Most planned capacity, 404.7 MW, will come from wind parks, while biomass-fuelled generators are supposed to add 56.8 MW, the article said.

Related Articles

bih croatia south interconnection pipeline intergovernmental agreement three seas kristo plenkovic

BiH, Croatia sign agreement on Southern Gas Interconnection

29 April 2026 - Bosnia and Herzegovina and Croatia have signed an intergovernmental agreement on the construction of the Southern Gas Interconnection

croatia grid connection fee hera decision

Croatia finally sets grid connection fee

29 April 2026 - The Croatian Energy Regulatory Agency (HERA) has adopted the fee for the connection to the electricity network

TerraPower Natrium Rendering nuclear power plant

TerraPower starts building 345 MW nuclear plant in US using advanced Natrium technology

29 April 2026 - The facility is set to become “the first utility-scale advanced nuclear power plant in the United States,” TerraPower said

Aktor LNG USA signs 20 year supply deal with Albania's Albgaz

Aktor LNG USA signs 20-year supply deal with Albania’s Albgaz

29 April 2026 - Aktor LNG USA and ALBGAZ signed a 20-year commercial agreement for liquefied natural gas (LNG) from the United States