In the first quarter of 2021, North Macedonia will launch an auction for the construction of solar power plants with installed capacity totaling 60 MW, which will be backed with feed-in premiums.

After successfully finishing the auction for the construction of 62 MW of solar photovoltaic installations in 2020, the country will organize similar bidding for another 60 MW, Prime Minister Zoran Zaev has announced on Facebook.

In 2019, North Macedonia organized auctions for the construction of solar PV plants backed with premiums on private and state land. In 2020, the government signed contacts with nine companies for investment in state land, and with 23 investors for projects on private land.

The new auction is expected to trigger EUR 35 million in investments

He said that several solar power plants have already been put into operation, adding that he expects the new auction to trigger investments of EUR 35 million.

The country is a true renewable energy leader in the region

Zaev said that there are so many arguments for the country to be considered a renewable energy leader in the region.

The construction of a 10 MW solar power plant is underway at a former coal mine in energy complex REK Oslomej, while two more facilities, with an installed capacity of 50 MW, will also be built, in an investment estimated at EUR 60 million, he said.

Three new PV plants with a total capacity of 160 MW are planned at energy complex REK Bitola

He has announced that grants have been secured for feasibility studies for three new PV plants with a total capacity of 160 MW at energy complex REK Bitola.

Power plant TEC Negotino has launched tendering for the preparation of a feasibility study, and in the first half of 2021 it will be assessed whether a new gas-fired power plant will be built in a public-private partnership project or whether the plant will be sold, he said, adding that the project could attract an investment of EUR 200 million to EUR 500 million.

The strategy for TEC Negotino will be chosen in the first half of 2021

The government earlier said it plans to switch the 210 MW power plant TEC Negotino from fuel oil to natural gas.

Zaev also said that 2021 will see the start of construction on the second phase of wind farm Bogdanci. The investment will increase the wind park’s installed capacity by 13.8 MW.

He also recalled that the Čebren hydropower project has attracted strong investor interest. Zaev said that the country is expanding its natural gas interconnections with Greece, and Kosovo*, and develops a retail network for households and businesses.

North Macedonia targets a 50% share of renewables by 2024

North Macedonia plans to reach a 50% share of renewables in electricity production by 2024 and to phase out coal.

The country is also in talks with General Electric to build a gas-fired power plant, and to switch power plant REK Bitola to gas.

State-owned energy company Elektrani na Severna Makedonija (ESM) has recently suspended investments in Bulgaria’s nuclear power plant Belene, and shifted its focus to the construction of a gas power plant in Greece.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Battery storage investors Romania rapidly expanding project pipeline

Battery storage investors in Romania rapidly expanding project pipeline

16 August 2025 - In an rising investment wave, firms in Romania are combining energy storage with solar, wind and hydropower or building standalone systems

north macedonia guarantees of origin solar power plant oslomej

Good start for North Macedonia: in first two months 100k+ guarantees issued

15 August 2025 - In April, the National Electricity Market Operator (MEMO) established the Register of Guarantees of Origin for electricity

Heat pump sales in Europe fell dramatically in 2024

Heat pump sales in Europe plunge in 2024

15 August 2025 - The EU wants to reach 60 million heat pumps by 2030, but sales in major European markets fell 22% in 2024

North Macedonia draft law envisages renewable energy auctions for CfDs

North Macedonia’s draft law envisages renewable energy auctions for CfDs

14 August 2025 - North Macedonia's draft Law on the Use of Energy from Renewable Sources covers auctions, CfDs, prosumers and renewable energy communities