Kosovo* ordered to compensate contractor over scrapped thermal power plant project Kosova e Re

kosova-e-re-contourglobal-arbitration-prishtina

Prishtina (photo: Leonhard Niederwimmer from Pixabay

Published

October 10, 2023

Country

Comments

comments icon

0

Share

Published:

October 10, 2023

Country:

Comments:

comments icon

0

Share

The International Court of Arbitration has ruled that Kosovo* must pay compensation to power generation company ContourGlobal over the cancelled project to build the Kosova e Re thermal power plant, according to an announcement from the Ministry of Economy of Kosovo*.

Kosova e Re, one of the last projects for the production of electricity from coal in the Western Balkans, was halted in 2020. The projected capacity of the power plant was 450 MW, and the investment was valued at about EUR 1.3 billion. A similar fate, according to recent reports, could befall the Tuzla 7 project in Bosnia and Herzegovina.

According to the Ministry of Economy, the court noted that the Kosova e Re project and the contracts signed with ContourGlobal, which was at the time based in the United States, were never in favor of Kosovo*.

The contract envisages compensation of EUR 20 million for ContourGlobal and EUR 8 million for Kosovo*

The amount of compensation that should be paid by Kosovo* was determined in advance under the contract, which was signed in 2017.

The predetermined compensation for ContourGlobal of about EUR 20 million, compared with EUR 8 million envisaged for Kosovo*, demonstrates how unequal the contract was, according to the ministry.

In March 2020, the company announced it was abandoning the thermal power plant project in Kosovo*, citing “the political situation.” The move followed the election of the government headed by Albin Kurti, while the contract was signed with the administration led by Ramush Haradinaj.

Implementing the project would have cost Kosovo* multiple times more than the unfavorable ruling

The company’s decision to withdraw from the project, according to the ministry, was fortunate given the high price of electricity under the contract and the ambition of Kosovo* to produce clean, affordable energy for citizens and industry.

Implementing the project would have cost Kosovo* multiple times more than the unfavorable arbitration ruling, the ministry said.

Kosovo* will now consider other legal remedies available, including filing a lawsuit with the competent court in London to seek the annulment of the arbitration ruling, according to the ministry.

The Kosova e Re project had encountered a number of problems even before it was stopped in March 2020. The World Bank decided not to finance it, while the Secretariat of the Energy Community launched a dispute over state aid for the project.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Most read articles on Balkan Green Energy News in 2025

Most read articles on Balkan Green Energy News in 2025

02 January 2026 - Battery storage and digitalization stepped into the spotlight in 2025, according to the readers of Balkan Green Energy News, which marked its tenth anniversary with the best results so far

serbia eps solar 1 gw Dubravka djedovic handanovic dusan zivkovic

Đedović Handanović: Construction of 1 GW solar project to start in 2026

31 December 2025 - The shareholders' assembly of of Elektroprivreda Srbije adopted the Three-Year Business Plan for the period 2026-2028

China commissions world largest open sea PV plant

China completes grid connection of world’s largest open sea PV plant

31 December 2025 - CHN Energy fully connected to the mainland grid a 1 GW solar power system that it built on the open sea off the coast of Shandong in China

Electrica call contractors for large PV parks in Romania

Electrica issues call for contractors for large PV parks in Romania

31 December 2025 - Electrica, in which the Romanian Government holds almost 50%, is again seeking contractors for its solar projects Satu Mare 3 and Bihor 1