Kosovo* ordered to compensate contractor over scrapped thermal power plant project Kosova e Re

kosova-e-re-contourglobal-arbitration-prishtina

Prishtina (photo: Leonhard Niederwimmer from Pixabay

Published

October 10, 2023

Country

Comments

comments icon

0

Share

Published:

October 10, 2023

Country:

Comments:

comments icon

0

Share

The International Court of Arbitration has ruled that Kosovo* must pay compensation to power generation company ContourGlobal over the cancelled project to build the Kosova e Re thermal power plant, according to an announcement from the Ministry of Economy of Kosovo*.

Kosova e Re, one of the last projects for the production of electricity from coal in the Western Balkans, was halted in 2020. The projected capacity of the power plant was 450 MW, and the investment was valued at about EUR 1.3 billion. A similar fate, according to recent reports, could befall the Tuzla 7 project in Bosnia and Herzegovina.

According to the Ministry of Economy, the court noted that the Kosova e Re project and the contracts signed with ContourGlobal, which was at the time based in the United States, were never in favor of Kosovo*.

The contract envisages compensation of EUR 20 million for ContourGlobal and EUR 8 million for Kosovo*

The amount of compensation that should be paid by Kosovo* was determined in advance under the contract, which was signed in 2017.

The predetermined compensation for ContourGlobal of about EUR 20 million, compared with EUR 8 million envisaged for Kosovo*, demonstrates how unequal the contract was, according to the ministry.

In March 2020, the company announced it was abandoning the thermal power plant project in Kosovo*, citing “the political situation.” The move followed the election of the government headed by Albin Kurti, while the contract was signed with the administration led by Ramush Haradinaj.

Implementing the project would have cost Kosovo* multiple times more than the unfavorable ruling

The company’s decision to withdraw from the project, according to the ministry, was fortunate given the high price of electricity under the contract and the ambition of Kosovo* to produce clean, affordable energy for citizens and industry.

Implementing the project would have cost Kosovo* multiple times more than the unfavorable arbitration ruling, the ministry said.

Kosovo* will now consider other legal remedies available, including filing a lawsuit with the competent court in London to seek the annulment of the arbitration ruling, according to the ministry.

The Kosova e Re project had encountered a number of problems even before it was stopped in March 2020. The World Bank decided not to finance it, while the Secretariat of the Energy Community launched a dispute over state aid for the project.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

europe solarpower Startup Awards 2026 reLi Energy

ReLi energy wins first prize at European Solar Startup Awards 2026

07 May 2026 - Germany’s reLi Energy won gold at the European Solar Startup Awards 2026. It has outperformed three other finalists to claim the top spot

Romania exceeds 1 GWh in battery storage capacity

Romania exceeds 1 GWh in battery storage capacity

07 May 2026 - Excluding prosumers, Romania has thirty battery energy storage systems (BESS) totaling 599 MW, while the overall capacity has surpassed 1 GWh

Enery inaugurates region largest battery system Nova Zagora in Bulgaria

Enery inaugurates region’s largest battery system in Nova Zagora in Bulgaria

07 May 2026 - Austria-based Enery has commissioned the Nova Zagora BESS. It is the largest battery system in Central and Eastern Europe, the company said.

Rezolv Energy 225 MW solar park St. George in Bulgaria

Rezolv Energy commissions 225 MW solar park St. George in Bulgaria

07 May 2026 - One of Bulgaria’s largest solar parks is now fully operational. Rezolv Energy built the St. George facility on the site of the former Silistra airport.