Electricity

BiH blocks Tuzla 7 coal plant project

BiH halts Tuzla 7 coal project state aid

Photo: EPBiH

Published

July 6, 2022

Comments

comments icon

0

Share

Published:

July 6, 2022

Comments:

comments icon

0

Share

The construction of unit 7 of the Tuzla thermal power plant encountered another obstacle with the decision of the State Aid Council of Bosnia and Herzegovina (BiH) to revoke its approval of the project. The contract for the 450 MW Tuzla 7 project was signed back in 2014.

The State Aid Council of BiH annulled its decision from 2018, when it found that a guarantee granted by the Federation of Bosnia and Herzegovina in favor of the Export-Import Bank of China for a loan to state-owned power utility Elektroprivreda BiH (EPBiH) for the Tuzla 7 project does not constitute state aid, the Energy Community Secretariat said.

The secretariat said that following its argumentation in an infringement case against BiH, the State Aid Council now decided that the guarantee constitutes illegal state aid, which the Federation’s Ministry of Finance is obliged to recover. The process was initiated in 2019.

Secretariat: The council accepted our arguments

The council’s move settles the infringement procedure, formally terminated by a decision of the Ministerial Council in 2021. It then found that Bosnia and Herzegovina has failed to comply with its obligations under article 18 of the Energy Community Treaty, which prohibits state aid.

A standstill due to the departure of General Electric

Chinese consortium Gezhouba Group and the Guangdong Electric Power Design Institute from China were hired to build the Tuzla 7 unit. The construction site has been ready since November 2020, but the activities were delayed after General Electric decided not to supply the equipment.

However, EPBiH later said it intended to continue the project and that it was looking for the best solution.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Nordex gets order for 70 MW wind power project Jasikovo in Serbia

Nordex gets order for 70 MW wind power project Jasikovo in Serbia

24 March 2026 - Nordex Group received an order for the supply and installation of eleven N175/6.X wind turbines for the Jasikovo wind farm in eastern Serbia

Serbian student team H-Bridges IEEE IFEC 2026 semifinals IEEE APEC conference

Serbian student team H-Bridges in IEEE IFEC 2026 semifinals at IEEE APEC conference

24 March 2026 - The H-Bridges student team from Serbia is in the semifinals of the International Future Energy Challenge (IFEC) competition in San Antonio, California, within the IEEE Applied Power Electronics Conference and Exposition.

World adds record 814 GW of solar wind in 2025

World adds record 814 GW of solar, wind in 2025

23 March 2026 - The world expanded its solar and wind power capacity by a record 814 GW altogether last year, or 17% more than in 2024, Ember found

entso e spain portugal blackout final report

ENTSO-E publishes final report on 2025 Spain, Portugal blackout

23 March 2026 - The report on the grid incident in Spain and Portugal on April 28 was produced by a technical expert panel of 49 members, ENTSO-E said