Albania’s Energy Regulatory Authority (ERE) said preparations are underway for the reconstruction of the 220 kV interconnection with Montenegro, but also that another line, of 110 kV, would link the two countries. A separate project is being developed for a 110 kV power line to Kosovo*.

Albania and North Macedonia are building their first power link, an overhead 400 kV line between Bitola and Elbasan, as part of the regional Corridor 8. Acknowledging the need for an increase in transmission capacities and their improvement, the Energy Regulatory Authority (ERE) of Albania said in its annual report that it plans to build secondary, 110 kV interconnectors with Kosovo* and Montenegro.

Albania counts on numerous renewable energy projects in its north and northeast and wants to increase its power export capacity

The existing 220 kV line between Vau i Dejës in Albania and Montenegrin capital Podgorica, with a capacity of 278 MVA, was built in 1972 and it needs to be reconstructed, the regulatory body said. It pointed to numerous initiatives for renewable energy projects in Albania’s north and northeast, requiring more reliable interconnectors with greater capacity.

ERE said a 110 kV overhead power line should be built from Velipoja in Albania to the Montenegrin seaside town of Ulcinj just across the border. The project is in an early phase, it underscored and added that cooperation needs to be established with the authorities in the neighboring country.

The project for another interconnection with Montenegro is in an early phase

The part of the interconnector on the Albanian side should be eight kilometers long. According to ERE, the border area has potential for wind power deployment.

The other planned 110 kV overhead line is envisaged to connect the substations in Bajram Curri and Kukës on the Albanian side with the neighboring areas in Kosovo*, ERE revealed.

The first interconnector, of 400 kV, was finished in 2016, but it was put into operation only in 2020, opening the way for the establishment of a joint power exchange. The project was worth EUR 70 million.

Albania produces almost all of its electricity in hydropower plants, but it is planning to diversify its energy mix and reduce the dependence on power imports.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Ministry of Energy Mining and Mineral Resources North Macedonia MoU Balkan Green Energy News Branislava Jovicic Sanja Bozinovska Balkan Energy Forum BEF 2026

Ministry of Energy, Mining and Mineral Resources of North Macedonia signs MoU with Balkan Green Energy News on cooperation and partnership

17 February 2026 - The Ministry of Energy, Mining and Mineral Resources of North Macedonia will expand its cooperation with Balkan Green Energy News in advancing the energy transition in the region

First Greek batteries to claim up to 157.000 euros per MW this year

First Greek batteries to claim up to EUR 157.000 per MW in 2026

17 February 2026 - The first standalone batteries to enter the system in Greece will get significant income, according to the electricity distribution system operator

serbia azerbaijan gas fired power plant agreement

Serbia, Azerbaijan sign agreement to build gas-fired power plant

16 February 2026 - The combined cycle plant is expected to have an installed capacity of around 500 MW, with the investment estimated at EUR 600 million

bih hydrogen project energoinvest epbih H2OIE cei

BiH starts working on national hydrogen strategy

13 February 2026 - The implementation of the CEI Support to Hydrogen Strategy Development and Know-How Transfer for BiH project began in Sarajevo