Renewables

Albania’s KESH to reconstruct its hydropower plant Fierza

Albania KESH reconstruct hydropower Fierza

Photo: European Union in Albania

Published

January 31, 2022

Country

Comments

0

Share

Published:

January 31, 2022

Country:

Comments:

0

Share

The Fierza hydropower plant in Albania, run by state-owned electricity producer KESH, is set to be upgraded to boost output by at least 10%. The EUR 50 million project is part of the Economic and Investment Plan for the Western Balkans.

The second-biggest hydropower plant in Albania is about to extend its life by at least 30 years. The Fierza facility, which was built in 1980 with an installed capacity of 500 MW, will have its turbines 1 and 3 overhauled and all four generators reconstructed, which is envisaged to boost output by at least 10%.

Minister of Finance and Economy Delina Ibrahimaj and state-owned power utility KESH’s Administrator Ergys Verdho have signed loan and grant agreements worth more than EUR 50 million in total with the Country Director of Germany’s KfW Development Bank Brit Horschke.

HPPs Fierza, Skavica are part of EU’s EUR 9 billion green plan for Western Balkans

Fierza is the first hydropower plant in the cascade on the river Drin (Drim). The project for its upgrade is part of the European Union’s Green Agenda for the Western Balkans and the related EUR 9 billion Economic and Investment Plan for the Western Balkans. The system’s reservoir has a volume of 2.7 billion cubic meters, of which 2.3 billion is used, according to data on KESH’s website.

KfW provided a EUR 40 million loan for the investment while the rest is covered by grants

United States–based Bechtel earlier won a contract to build hydropower plant Skavica upstream in the country’s northeast, near the border with North Macedonia. It is also one of the green agenda projects for the region. The company is working on feasibility and social and environmental impact studies.

Ambassador of Germany Peter Zingraf noted that his country provided a EUR 40 million loan and a EUR 2 million grant through KfW for Fierza and that they were complemented by a grant of EUR 8.35 million within the Western Balkans Investment Framework (WBIF).

KESH is preparing for its role in liberalized power market

Minister of Infrastructure and Energy Belinda Balluku said the hydropower plant is covering 22% of the country’s electricity needs or 1.33 TWh per year but that it is in a poor condition due to lack of investment. Annual losses have reached 4%, she stressed.

The reconstruction will enhance KESH especially with regard to its future role as an energy supplier in the liberalized market in Albania and the region, in Balluku’s view. Domestic power demand has lately climbed as much as 90% from its usual level for this time of the year amid cold weather, but also the rebound from the pandemic impact, she said.

Downstream from Fierza is hydropower plant Koman, with a capacity of 600 MW, followed by the Vau i Dejës system of 250 MW, the last in the cascade. It is located in Albania’s northwest.

Minister Ibrahimaj said KfW has committed EUR 778.6 million for investments in the country so far, of which 40% in the energy sector, followed by 36% for water supply and sewerage.

Albania is almost 100% dependent on hydropower for its domestic electricity production, which makes it vulnerable to changes in hydrological conditions. The government, which declared a state of energy emergency in October, has high hopes in the deployment of wind and solar power plants.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Mitsubishi Power commissions desulfurization system Serbia s TENT A coal plant

Mitsubishi Power commissions desulfurization system in Serbia’s TENT A coal plant

25 April 2024 - Serbia finally got its second coal plant desulfurization system, in TENT A in Obrenovac near Belgrade, so the air is about to become cleaner

eu necp solar targets grids flexibility solarpower europe

EU countries update NECPs: 2030 solar goals lifted by 90% but grids lag

25 April 2024 - SolarPower Europe said grid and flexibility planning trail far behind renewables goals, putting the energy transition at risk

Slovenia-Energy-Act-bolster-efficiency-decarbonization

Slovenia amends Energy Act to bolster efficiency, decarbonization

25 April 2024 - The changes to Slovenia's Energy Act introduced incentives for renewables, decarbonization of coal regions and energy efficiency measures

China’s energy transition on track for carbon neutrality by 2060

24 April 2024 - China is making huge progress toward its goal of reducing net emissions to zero, Norwegian consulting firm DNV estimated in a report