CW Enerji to tap on subsidies in Turkey for solar panel factory project

CW Enerji to tap on subsidies in Turkey for solar panel factory project

Photo: iStock

Published

August 4, 2025

Country

Comments

comments icon

0

Share

Published:

August 4, 2025

Country:

Comments:

comments icon

0

Share

CW Enerji earmarked USD 520 million for the expansion of its solar panel manufacturing capacity in Antalya to 5 GW per year. It said it would benefit from the government’s HIT-30 incentives program.

While Europe is stagnating in solar panel production and some large facilities are even closing under pressure from China’s increasing global dominance, Turkey is expanding its industrial base across new green energy technologies. CW Enerji is about to invest USD 520 million in the construction of a photovoltaic equipment factory, Anadolu Agency reported.

The company said it would implement the project under the government’s HIT-30 incentives program for high technology. The location is in AOSB – Antalya Organized Industrial Zone in the country’s southern, Mediterranean region.

High domestic content enables access to subsidies

CW Enerji’s new facility, would complement the existing CW Solar Cell factory. It makes up to 1.2 GW of TOPCon high-efficiency solar cells per year and the company claims it is the largest in Europe.

The upcoming investment would enable an annual capacity of 5 GW by the end of the second phase, in 2028, according to the company. The products would have a domestic content of more than 80%, complying with the requirements for tax incentives, CW Enerji’s Chairman Tarık Sarvan said.

He founded the company in Turkey in 2010. It also makes other components and provides installation and maintenance services. CW Enerji has established subsidiaries in Munich, Germany, and Houston, Texas. Total solar panel capacity is 1.8 GW per year and it exports to nearly 60 countries, Sarvan added. He pointed out that the company’s target markets are the United States and Europe.

Dozens of companies manufacturing PV equipment in Turkey

Right before CW Enerji’s announcement, Astronergy allocated USD 700 million for its second solar module factory, in Balıkesir.

Early this year, 75 solar panel manufacturers operated in Turkey. Put together, their annual capacity was 44.5 GW. Three were making solar cells and their overall capacity was 6.1 GW per year.

The country is also strong in other technologies, like for geothermal power plants.

The government recently declared a 2035 target for solar and wind of 120 GW in total. At the end of June, Turkey’s total electricity capacity was 119,6 GW, of which photovoltaics accounted for just under 23 GW.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

BEF 2026 reveals new wave of sponsors as Belgrade prepares to host regional energy elite

BEF 2026 reveals new wave of sponsors as Belgrade prepares to host regional energy elite

13 April 2026 - Belgrade Energy Forum – BEF 2026 has expanded its partner network and is welcoming another group ranging from renewable energy giants to industrial associations.

croatia wind farm cemernica vsb totalenergies

TotalEnergies developing 80 MW Čemernica wind farm in Croatia

10 April 2026 - The Čemernica wind farm is planned to be built in the municipality of Dicmo and the city of Trilj, near the coastal city of Split

eu first cbam certificate price european commission

European Commission sets first CBAM certificate price

10 April 2026 - The European Commission has published the first price of CBAM certificates for 2026 Q1 on its new dedicated page on the CBAM website

Serbia’s Đedović Handanović in Azerbaijan for discussions on gas projects

08 April 2026 - Serbian Minister Dubravka Đedović Handanović met in Baku with Azerbaijani ministers and the head of SOCAR