Imports from China don’t exceed 26% of PV project costs in Romania

Nedea Solar equipment China 26 project costs Romania

Photo: Pvproductions on Freepik

Published

February 3, 2025

Country

Comments

comments icon

0

Share

Published:

February 3, 2025

Country:

Comments:

comments icon

0

Share

Iulian Nedea, CEO of Simtel, listed the costs for the construction of a solar power plant of 1 MW in peak capacity in Romania. Photovoltaic panels imported from China make up 20% and inverters account for 6%, he calculated. Separately, the head of the domestic EPC firm said the country can achieve energy independence with solar power plants occupying just 0.03% of its agricultural land.

In a post on social networks, President of the Board of Directors and Co-founder of Simtel Iulian Nedea argued against the notion that investments in solar power mainly benefits foreign economies and especially China’s. He outlined an example of a project for a ground-mounted unit of 1 MW in peak capacity in Romania.

Engineering, procurement and construction (EPC) firm Simtel Team, which also develops its own projects, needs EUR 500,000 on average, according to Nedea’s calculation. The expenses range between EUR 400,000 and EUR 600,000, he added.

Inverters don’t need to be from China

The CEO valued solar power panels imported from China at EUR 100,000, which is one fifth of the budget. Inverters make up another 6%, though Simtel often buys ones manufactured in the European Union, Nedea explained. He stressed that everything else are Romanian and EU products and services.

Racking, the metal structure holding the modules, has an 11% share while a substation amounts to 10%. The price of cables is 9.6% of the total, compared to 4.4% for the rest of the hardware and roads, the list reads. Project design, labor costs, fuel and miscellaneous costs are 27.1% overall. Nedea attributed the remaining 11.9% to profit before tax.

Investments in photovoltaic parks not only support the transition to green energy, but also stimulate the local economy, in his view.

Solar power targets in Romania can be achieved with zero impact on agriculture

Separately, Nedea addressed the question whether Romania is sacrificing agricultural land for renewable energy, Economedia reported.

The head of Simtel said 5,000 hectares are required for the estimated 5 GW in solar power by 2030 in peak terms. It is equivalent to only 0.06% of Romania’s agricultural land, he said. However, half of all PV systems are built on roofs, contaminated and devastated land, Nedea pointed out.

If projects for the remaining 0.03% are only on degraded agricultural land, the impact on agriculture would be zero, he underscored.

Nedea also said Romania has 780,000 hectares of arable land affected by desertification. As for profitability, he claims investors in solar power pay landowners EUR 850 to EUR 2,500 per hectare per year, “an amount that far exceeds a farmer’s annual net profit, especially in drought conditions or fluctuating grain prices.”

Average output from 1 MW of solar power capacity in the country is 1.4 GWh, Nedea noted.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

nuscale small modular reactor smr fluor sale

US-based Fluor sells remaining stake in NuScale, technology supplier for Romania’s SMR project

27 April 2026 - Since September 2025, Fluor has earned a total of USD 2.43 billion from the sale of NuScale shares

bih elektroprivreda republike srpske ers loss 2025 trebinje petrovic

BiH’s power utility ERS reports EUR 29 million loss in 2025

27 April 2026 - Elektroprivreda Republike Srpske CEO Luka Petrović said the company operated under extremely difficult circumstances last year

New Akuo Southeastern Europe interview Bruno Bensasson

New Akuo is powering up in Southeastern Europe

27 April 2026 - The energy crisis is underscoring the necessity of renewables for energy security, alongside climate goals and competitiveness, CEO of Akuo Bruno Bensasson tells Balkan Green Energy News

croatia geolgical co2 storing ccs agency balen susnjar krpan

Croatia to analyze potential for geological CO2 storage

27 April 2026 - A grant agreement for the carbon dioxide capture and storage project was signed as part of the National Recovery and Resilience Plan