Leaked paper shows Romania’s power sector coal-free in 2026

Leaked paper shows Romania power sector coal free 2026

Photo: iStock

Published

August 2, 2024

Country

Comments

comments icon

0

Share

Published:

August 2, 2024

Country:

Comments:

comments icon

0

Share

Transelectrica reportedly doesn’t see coal power plants having any share in Romania’s transmission system in 2026 and beyond. The official phaseout deadline is 2032.

Romania’s electricity transmission system operator Transelectrica is working on a ten-year plan through 2033. According to media reports, the draft shows coal power gone already in 2026. A similar announcement has just emerged in Greece, while Bulgaria is struggling even to keep its sole state-owned facility online.

Until a few years ago, the three countries were hesitating to determine coal phaseout dates or delaying them. Now even newer or reconstructed plants of the kind across Europe are reducing capacity utilization or abruptly shutting down. For instance, the ContourGlobal Maritsa East 3 coal-fired power plant in Bulgaria recently fired almost all its employees.

The ContourGlobal Maritsa East 3 coal-fired power plant in Bulgaria recently fired almost all its employees

Expenses are high because of the allowances that producers must buy via the European Union’s Emissions Trading System (EU ETS). They also face ever stricter environmental requirements. It makes coal power uncompetitive.

On the other hand, an uncontrolled collapse of the sector could jeopardize the security of energy supply. The rapid cut in coal power capacities makes the region’s energy consumers vulnerable to cold spells in the winter.

Romania leans on gas power to cover 2026 coal exit

The market has decimated coal plant production. In Romania in particular, it is evident from the forced transformation of state-owned coal miner and power plant operator Complexul Energetic Oltenia (CE Oltenia).

Active coal plants had an overall 1.9 GW in April, compared to 5.3 GW in 2012. CE Oltenia plans to replace them with gas power facilities in Ișalnița and Turceni by 2026, while with projects of other Romanian energy companies like Electrocentrale Bucharest (ELCEN), the new capacity is seen at 4.5 GW

Romania is officially planning to complete its coal phaseout in 2032.

Would be worse without renewables

Minister of Energy Sebastian Burduja recently said Transelectrica’s report would determine the parts of the national electricity system that are in deficit. The last heat wave disturbed the wholesale trade in the region and catapulted power prices.

Burduja insisted that the situation would have been much worse without renewables.

The authorities want to eliminate coal by 2026 because Romania will double its interconnection capacity with neighboring countries to 7 GW next year, Radu Miruță said. He is a member of parliament from the opposition Save Romania Union (USR) and its head in Gorj county, a major coal hub. The country is upgrading the interconnections to buy, not to sell, in Miruță’s view.

The fate of coal industry workers and entire communities hangs in the balance. The implications are serious for national economies as well. The European Union’s just transition programs seem to need a boost.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ACER Zinglersen Integrate electricity markets flexibility new era already here BEF 2025

ACER’s Zinglersen: Integrate electricity markets to bolster flexibility as new era is already here

28 May 2025 - The number of hours with negative power prices reached an all-time high for two years in a row, which means a new era is here, ACER's Director Christian Zinglersen said at BEF 2025

NGEN BEF 2025 decentralized electricity grid Roman Bernard BEF 2025

NGEN showcases solutions at BEF 2025 for decentralized electricity grid of tomorrow

28 May 2025 - Slovenia-based NGEN is expanding throughout Europe with its software platforms and equipment and BESS for decentralized grids

belgrade energy forum bef 2025 flexibility services batteries koer ngen ems alteo cybergrid

BEF 2025: Digitalization, open markets, time are major preconditions for flexibility services mainstreaming

27 May 2025 - The panel called Market Flexibility: The Backbone of a Resilient Energy System was one of the eight sessions at Belgrade Energy Forum 2025

Fortis Energy Gavrilovic developing huge portfolio in SEE

Velimir Gavrilović, Fortis Energy: We are developing huge portfolio in SEE

27 May 2025 - Fortis Energy is working on renewable energy projects of 2 GW altogether in Southeast Europe, of which half is in Serbia