2 GW of renewable energy projects apply for grid connection in Bulgaria

2 GW renewable energy grid connection Bulgaria

Photo: Zsuzsa Bóka from Pixabay

Published

May 19, 2021

Country

Comments

comments icon

0

Share

Published:

May 19, 2021

Country:

Comments:

comments icon

0

Share

The Electricity System Operator (ESO) of Bulgaria received requests from 22 investors since the beginning of the year for connecting renewable energy plants under development to the grid. Their combined capacity is 1.97 GW.

Huge interest in the construction of large power plants using renewable sources was registered since the end of last year in Bulgaria. Capital.bg reported, citing data provided by the Electricity System Operator or ESO, that 22 investors applied for approval for grid connection for power plants with a planned capacity of 1.97 GW in total.

In comparison, the national transmission system operator (TSO) received 14 requests for an overall 480 MW in the same period of 2020. The news outlet adds there is currently 2 GW in operating renewable power plants in the country excluding hydropower.

New law helps investment in renewables

Bulgaria recently amended its Energy Act, boosting support for new renewables. Projects put into operation after January 1 are exempted from paying 5% of revenue to the Electricity System Security Fund. The rule doesn’t apply for rooftop solar power installations as they are entitled to preferential prices.

ESO didn’t make its available network capacity public, so investors may develop projects in wrong places

So far in 2021, ESO issued opinions on the possibility of connecting seven renewable power plants to the grid. Total planned capacity is 364 MW. It also signed preliminary contracts with four investors for 190 MW in new green energy facilities, according to the article.

Solar power plant of 3.2 MW comes online

Eleven rooftop solar power systems of 30 kW each were connected to the grid since January 1, together with Trakiya MT’s 3.2 MW solar power plant in Malko Tarnovo near the border with Turkey.

The report highlights the fact that ESO didn’t make its available network capacity public, which means investors may get a negative opinion even after they purchase land for renewable energy plants and obtain various permits.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

masdar socar green solar power projects azerbaijan

Masdar, SOCAR join forces on 760 MW of solar in Azerbaijan

23 November 2024 - Masdar and SOCAR Green have reached financial close for the 445 MW Bilasuvar and 315 MW Neftchala solar projects in Azerbaijan

wind farm ljubusa tomislavgrad

Concession signed for 80 MW wind farm in Tomislavgrad

22 November 2024 - Alpha Wind has been granted a concession to build the 80 MW Ljubuša wind farm in the municipality of Tomislavgrad.

Greece, EU establish Islands Decarbonization Fund

Greece establishes Islands Decarbonization Fund with EU

22 November 2024 - The Islands Decarbonization Fund was launched in Naxos, with financing from the European Investment Bank

montenegro gvozd epcg nordex Ibrahim Özarslan

Montenegro’s power utility EPCG begins construction of Gvozd wind farm

21 November 2024 - Wind farm Gvozd will be the first large-scale power generation facility to be built by EPCG in more than 40 years