Works begin on EUR 13.5 million Kragujevac-Kraljevo transmission line

Kragujevac-Kraljevo transmission line

Photo: EMS

Published

June 17, 2020

Country

Comments

comments icon

0

Share

Published:

June 17, 2020

Country:

Comments:

comments icon

0

Share

For the first phase of the construction of the Trans-Balkan Electricity Corridor, worth EUR 157 million, EMS is using KfW’s EUR 15 million loan and another EUR 6.5 million from European funds. The construction of the Kragujevac-Kraljevo overhead power link is the project’s second section out of four.

A ceremony was held for the start of the construction of a 400 kV overhead power line that will link Kragujevac and Kraljevo in Serbia. The works are part of the second part of the first phase of the Trans-Balkan Electricity Corridor. According to the schedule, they must be finished in 610 days.

The entire 220 kV network and the equipment, which is 50 years old on average, will be replaced, said General Manager of Elektromreža Srbije (EMS) Jelena Matejić. “We are creating a new reality and bringing new possibilities for development. Nowhere in the world is there economic progress or investment without an adequate and reliable electric power infrastructure”, she underscored and stressed losses in power would be lowered and, with them, the carbon dioxide emissions.

The second section is worth EUR 29.6 million in total

The length of the power link between substations Kragujevac 2 and Kraljevo 3 will be sixty kilometers, and the contract is worth EUR 13.5 million. Kodar energomontaža is the consortium lead and Elektromontaža from Kraljevo and Elnos BL from Banja Luka in Bosnia and Herzegovina are its members.

The aforementioned second section, valued at EUR 29.6 million, includes upgrading substation Kraljevo 3 to 400 kV and equipping Kragujevac 2 with one 400 kV feeder bay. The investment in the first part came in at EUR 27 million, while EUR 100 million is envisaged for the third and fourth section. It means EUR 157 million would be spent on the first phase of the Trans-Balkan Electricity Corridor: from Serbia’s border with Romania to Montenegro, EMS said.

Antić: The Kragujevac-Kraljevo power line is necessary for the construction of pumped storage hydropower plant Bistrica

The entire project will link Ukraine with Italy across Southeastern Europe and enable the development of energy projects and power trading, Minister of Mining and Energy Aleksandar Antić said. The section from Pančevo to the Romanian border integrated wind power plants in Banat region into the system, and the Trans-Balkan Electricity Corridor is one of the key tools for using renewable energy potential, he asserted.

“By building this overhead electricity line, we will enable a more stable operation of hydropower plant Bajina Bašta, and the connection is one of the key steps for the construction of pumped storage hydropower plant Bistrica, which is one of the most important strategic projects,” Antić added and stressed the project design is underway for the section between Obrenovac and Bajina Bašta.

The project design is underway for the section between Obrenovac and Bajina Bašta

Germany’s KfW Development Bank provided a EUR 15 million loan, supported by Serbia’s sovereign guarantee to EMS, the state’s transmission system operator or TSO. Another EUR 6.5 million is a grant allocated through the European Union Western Balkans Investment Framework from the European Western Balkans Joint Fund. EMS also invested own funds.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

energy storage battery europe

Europe’s energy storage capacity to reach 100 GW this year, more than double by 2030

21 November 2025 - Pumped hydropower has the largest share of existing energy storage, 50.6 GW, followed by batteries, with 44.8 GW

3rd Conference on Advancing Renewable Investments guarantees of origin could drive Europe green energy integration

3rd Conference on Advancing Renewable Investments – guarantees of origin could drive Europe’s green energy integration

21 November 2025 - As CBAM nears implementation, the Ljubljana conference highlighted the tools to accelerate integration with the EU, the Energy Community Secretariat said

montenegro admir sahmanovic energetika teska godina pljevlja potrosnja struje

Šahmanović: Montenegro is facing its most challenging year for energy sector

20 November 2025 - Priorities are price stability, increasing the use of renewables, and strengthening the country's position as an energy hub, Šahmanović said

Alcazar take over NIAT wind farm 500 MW in Egypt Siemens Gamesa after completion

Alcazar to take over NIAT wind farm of 500 MW in Egypt from Siemens Gamesa after completion

20 November 2025 - Alcazar formalized the partnership for the final development, construction and operation of Siemens Gamesa's NIAT wind project in Egypt