ESO receives grant for Maritsa-Nea Santa power line, CESEC updates Electricity Action Plan

Photo: ESO

Published

April 4, 2019

Country

Comments

0

Share

Published:

April 4, 2019

Country:

Comments:

0

Share

The Bulgarian Electricity System Operator (ESO) and the Innovations and Networks Executive Agency of the European Commission have signed a EUR 28.6 million grant agreement under the Connecting Europe Facility (CEF) for the construction of the Bulgarian section of the 400 kV power line Maritsa East (Bulgaria)-Nea Santa (Greece).

The agreement was signed during the VI meeting of the Central and South Eastern Europe Energy Connectivity (CESEC) High Level Group in Bucharest. The meeting has ended with conclusions and the updated Electricity Action Plan for the region.

The CESEC High Level Working Group was set up by Austria, Bulgaria, Croatia, Greece, Hungary, Italy, Romania, Slovakia and Slovenia and the EU in 2015, while eight Energy Community contracting parties joined later.

At the end of January this year, the CEF Coordination Committee decided to grant up to EUR 28.6 million to Bulgarian transmission system operator (TSO) ESO for the second interconnector between Bulgaria and Greece.

The total cost of the project is EUR 57.3 million, and ESO will secure the rest from its own funds, ESO said in a news release.

The power line is 123 km long on Bulgarian territory and 29 km on Greek territory and has a capacity of 1,500 MW. The interconnector should be operational by June 2023.

The power line will strengthen the 400 kV grid in the region, significantly increase the possibility of electricity exchange between the two countries and support renewable energy projects in Northeastern Greece and South Bulgaria, ESO said.

CESEC Electricity Action Plan updated

According to the European Commission’s website, the meeting allowed Climate action and Energy Commissioner Miguel Arias Canete and Ministers of Energy or high level representatives of EU Member States and Energy Community contracting parties to discuss common priorities for the future on gas and electricity markets and infrastructures, as well as on renewables and energy efficiency.

In conclusions, the High Level Group has stressed the need to make rapid progress in the implementation of the electricity market coupling projects between EU Member States and Energy Community contracting parties, as identified in the updated CESEC Electricity Action Plan.

The plan numbers immediate actions needed for the power trading and coupling of electricity markets, including Italy-Greece-Bulgaria market coupling (MC), Albania-Italy-Montenegro-Serbia (AIMS), Bulgaria-Romania-Greece + accession stream for the future Western Balkan 6 partners with Croatia, Hungary, and Italy, Croatia-BiH MC, Bulgaria – North Macedonia MC, and Croatia-Serbia-Bulgaria MC.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

drina-hydropower-plants

Court annuls environmental permit for Drina hydropower project

02 May 2024 - The construction of large hydropower plants on the Drina is facing new delays, after a court ruling to scrap the environmental permit for HPP Foča

el-dorado-electricity-imports-north-macedonia-rke

North Macedonia: ‘Solar El Dorado’ cuts electricity imports to 2.75%

02 May 2024 - In 2023, North Macedonia's new solar capacity increased by as much as 251% compared to 2022

EU-completing-Green-Deal-Industrial-Plan-Net-Zero-Industry-Act

EU completing Green Deal Industrial Plan as Net Zero Industry Act awaits go-ahead

01 May 2024 - The European Union's Net Zero Industry Act is about to come into force, completing legislative work within the Green Deal Industrial Plan

Dubravka Dedovic Djedovic Handanovic reappointed Serbia minister of energy mining

Dubravka Đedović Handanović reappointed as Serbia’s minister of energy, mining

30 April 2024 - Minister of Energy and Mining Dubravka Đedović Handanović is keeping her seat in the new cabinet while Minister of Environmental Protection Irena Vujović is also becoming deputy prime minister