EPHZHB breaks ground for 66 MW Vrilo pumped-storage hydropower plant

Photo: Pixabay

Published

July 16, 2018

Comments

comments icon

0

Share

Published:

July 16, 2018

Comments:

comments icon

0

Share

Public power utility Elektroprivreda Hrvatske Zajednice Herceg Bosne (EPHZHB) held a groundbreaking ceremony for the Vrilo pumped-storage hydropower plant on the Šuica sinking river near Tomislavgrad on July 16 .

The Vrilo pumped-storage hydropower plant, to be built in an investment worth EUR 89.1 million, is designed to have two units with a total installed capacity of 66 MW, with operations planned to begin in 2023. The plant’s annual electricity output is projected at 196 GWh, according to an announcement on the company’s website.

EPHZHB is majority owned by the Federation of Bosnia and Herzegovina (FBiH) and is one of the Bosnian entity’s two power utilities. The entity of Republika Srpska also has a power utility.

Mostar-based EPHZHB reported a profit of BAM 237,441 (about EUR 120,000) in 2017, which it used for covering losses from previous years. It produced 1,287 GWh of electricity last year, down 18.26% compared to the planned level due to drought.

The company produces electricity solely from renewable energy sources, with most of its capacities consisting of hydropower plants.

Earlier this year, EHZHB unveiled Mesihovina, Bosnia and Herzegovina’s first wind farm.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Electrica install 500 MW solar park Liberty Galați steel plant in Romania

Electrica to install giant solar park with storage at Liberty Galați steel plant in Romania

26 February 2026 - Electrica agreed with inactive steel plant Liberty Galați to jointly develop solar power and energy storage capacities of up to 500 MW

north macedonia just transition employees training bitola

Over 600 workers in North Macedonia complete training under just transition projects

26 February 2026 - The projects are part of North Macedonia's Just Transition Investment Platform, launched in 2023, launched by the government

Greek IPTO postpones new island interconnections, proposes higher revenue limit

Greece’s IPTO postpones island interconnections, proposes higher revenue limit

26 February 2026 - New power interconnections between mainland Greece and the Dodecanese and Northern Aegean islands have been...

eu russia natural gas ban energy community

EU decision to ban Russian gas is legal grey zone from Energy Community’s perspective

26 February 2026 - The Energy Community Secretariat is organizing the Vienna Forum on European Energy Law, in partnership with Kinstellar