45 MW Brežice hydropower plant on river Sava inaugurated

Photo: HESS

Published

October 2, 2017

Country

Comments

comments icon

0

Share

Published:

October 2, 2017

Country:

Comments:

comments icon

0

Share

The Brežice hydropower plant (HPP), the largest and fifth in the chain of six hydroelectric power plants on the lower Sava river, in Slovenia, was inaugurated last week. According to the Slovenian media, the construction costs are estimated at EUR 261 million. The construction of 45 MW HPP was launched in March 2014.

It is a hydroelectric power plant of the run-of-the-river and reservoir type, with three vertical generating units with a combined rated discharge of 500 m3/s, five spillways and an average annual production output of 161 GWh.

HPP Brežice will make up roughly one percent of Slovenia’s present annual electricity production and will also provide peak-load power and open up possibilities for selling ancillary services. This power plant is going to be fully automated, unmanned and remotely operated from the control centre.

The initiative to start the procedure for the preparation of the National Spatial Plan for HPP Brežice was launched in 2006.

Hidroelektrarne na Spodnji Savi (HESS), a Slovenian hydroelectric power company, was established in 2008 with the core mission to facilitate and promote the construction of new HPPs thus engaging in sustainable, reliable, competitive and environmentally friendly power production.

Despite the financial setbacks the company faced in 2016, the technical inspection and start of trial operation are scheduled for the end of September 2017.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

montenegro epcg solar gradnja solar power plants

EPCG Solar Gradnja installs 36 MW of solar power in 2025

15 December 2025 - EPCG Solar Gradnja specializes in the procurement, design, installation, and maintenance of photovoltaic systems

world ember bess solar energy storage cost capex lcos

Solar power has become dispatchable anytime at low cost

15 December 2025 - Ember’s assessment of energy storage costs is based on recent auctions in Italy, Saudi Arabia and India and on expert interviews

AI and Energy: the dynamic duo shaping the power grid

AI and Energy: the dynamic duo shaping the power grid

15 December 2025 - How artificial intelligence is reshaping power grids, enabling renewable energy integration while raising regulatory, ethical and sustainability challenges.

nova bess romania battery

Romania’s biggest battery system put into operation

13 December 2025 - Nova Power & Gas has commissioned a battery energy storage system with an operating power of 200 MW and a capacity of 400 MWh