Works beginning on North Macedonian side of gas interconnector with Greece

Works beginning North Macedonian side gas interconnector with Greece

Photo: Ministry of Energy, Mining and Mineral Resources

Published

May 8, 2025

Comments

comments icon

0

Share

Published:

May 8, 2025

Comments:

comments icon

0

Share

The North Macedonian section of the gas interconnector with Greece is expected to be completed by early 2027. The construction contract was signed by the Ministry of Energy, Mining and Mineral Resources, domestic contractor Rapid Build and the country’s gas transmission system operator Nomagas.

The construction of the gas pipeline connecting North Macedonia with Greece is set to begin in a month, according to officials. Land expropriation is 90% complete. The initial capacity of the interconnector would be 1.5 billion cubic meters per year, with a potential to double it. The works are expected to be completed within 22 months.

„With the signing of the contract for the construction of the Macedonian section of the gas interconnector with Greece, we are marking the beginning of the largest energy investment in North Macedonia in the last ten years. The interconnector is proof that when there is political will, regional trust, and professional dedication – the results are real and tangible,” said Minister of Energy, Mining and Mineral Resources Sanja Božinovska.

The contract was signed by the ministry, contractor Rapid bild, based in Kumanovo in North Macedonia, and the country’s gas transmission system operator Nomagas. The future pipeline would be able to carry both natural gas and hydrogen.

North Macedonian gas interconnector Greece

Repeated tender slashes price by EUR 12 million

The winning bid was EUR 59.9 million or EUR 12 million less than in the initial tender, which was annulled.

The project is worth over MKD 5.1 billion (EUR 82.9 million). It is financed by the European Investment Bank (EIB) and the European Bank for Reconstruction and Development (EBRD). It includes grants of EUR 2.5 million for technical assistance and another EUR 9.9 million via the Western Balkans Investment Framework (WBIF).

The project is financed by the EIB and EBRD

„This contract ensures diversification and access to a greater number of natural gas sources, enables economic development, progress and environmental protection, and contributes to the security of energy supply,” said Executive Director of Nomagas Muhamet Elmazi.

Gasification would significantly improve air quality, especially in areas where wood and fuel oil are currently used for heating.

Greek section of interconnector under construction since February

On the North Macedonian side, the interconnector route is 68 kilometers long, out of a total of 123 kilometers. It will run from Nea Mesimvria in Greece through Evzoni (Mačukovo) and Gevgelija at the border, to Negotino. The next phase involves building gas links from Gostivar to Kičevo (34 kilometers) and from Sveti Nikole to Veles (28 kilometers).

Greek company Terna began constructing its country’s section of the pipeline in February.

Nomagas and Greece’s National Natural Gas System Operator (DESFA) made their final investment decision a year and a half ago.

The companies leaned the investment on the project for the Alexandroupolis LNG Terminal. The liquefied natural gas facility in northeastern Greece was opened on October 1. However, due to a malfunction, it has been out of operation for more than three months. According to the latest update, gradual reactivation is expected to begin by the end of May.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

sany renewable energy bef 2025

SANY Renewable Energy makes successful breakthrough in European market

20 May 2025 - At BEF 2025, SANY Renewable Energy showcased its cutting-edge wind power technology and integrated solutions to the European market

GGF Kostadinov Western Balkans responded energy crisis innovation ambition

GGF’s Kostadinov: Western Balkans responded to energy crisis with innovation, ambition (video)

20 May 2025 - The past three to four years have been nothing short of transformational when it comes to the energy transition in the Western Balkans, said Borislav Kostadinov, Finance in Motion's Fund Director for GGF

Construction of the largest solar power plant in Bosnia and Herzegovina begins

Construction of largest solar power plant in Bosnia and Herzegovina begins

20 May 2025 - Aurora Solar started building a 125 MW solar power plant near Stolac. It is set to become the largest in Bosnia and Herzegovina.

Wind farms turned Greece into a net exporter of electricity

Wind farms turn Greece into net exporter of electricity

20 May 2025 - Wind energy played a crucial role in turning Greece into a net electricity exporter last year, for the first time since 2000