Electricity

Nuclear power plant Krško back online after emergency repair

Nuclear plant Krsko back online emergency repair

Photo: NEK

Published

November 20, 2023

Country

Comments

comments icon

0

Share

Published:

November 20, 2023

Country:

Comments:

comments icon

0

Share

Parts of pipelines on both sides of the reactor vessel in the Krško nuclear plant were replaced as a precaution due to a leakage detected on the reducer section in early October. The facility was reconnected to the power network and its capacity utilization is being gradually increased.

The Krško nuclear power plant was resynchronized with the electricity grid after it was preventively shut down on October 6 due to a leak. Slovenia’s power system stability was put under an additional test with an outage of unit 6 in the Šoštanj coal-fired power plant last week because of a malfunction in the transportation of slag from the boiler. The other unit wasn’t affected.

Both facilities came back online on November 17. Combined, the nuclear and thermal power plant account for two thirds of the country’s domestic electricity output. It should also be noted that Slovenia covers 30% of its power consumption from imports.

Regular overhaul due in April

Krško was relaunched with a capacity utilization rate of 28%, which is being gradually increased, according to its operator NEK. It is a joint venture of Slovenian government-controlled utility GEN energija and Croatia’s Hrvatska Elektroprivreda (HEP Group).

Krško has 696 MW in capacity. It is scheduled for an overhaul in April. Slovenia is planning to build another nuclear power plant.

Westinghouse handles repair

As for the leakage, detected on October 4, the hole was within the primary cooling circuit, in the reducer section of the pipeline. It was on a high-pressure safety injection system, which is one of the emergency core cooling systems.

Westinghouse, the original designer and equipment supplier, repaired the malfunction, helped by domestic companies. Sections of pipelines on both sides of the reactor vessel were replaced until the check valves.

All 121 fuel elements were transferred to the spent fuel pool to enable the repair.

NEK said it is already contracting metallographic research and thermohydraulic and mechanical analyses to determine and analyze the cause of the failure. It plans to complete the examinations within one year.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Akuo sustainable growth green energy workshop Stip

Akuo leads way for sustainable growth by organizing green energy workshop in Stip

05 March 2025 - Akuo hosted a collaborative workshop in partnership with the Goce Delčev University Shtip in North Macedonia

Nofar Energy commissions Serbia largest solar park

Nofar Energy commissions Serbia’s largest solar park

05 March 2025 - Nofar Energy said its photovoltaic park in northern Serbia of 27 MW in peak capacity began delivering electricity to the grid

IC Enterra 136 MW solar power plant operation Turkey

IC Enterra puts 136 MW solar power plant into operation in Turkey

04 March 2025 - IC Enterra gradually completed the Erzin-2 facility, of 136 MW in peak capacity. It won the project at a renewables auction in 2022.