Electricity

Nuclear power plant Krško back online after emergency repair

Nuclear plant Krsko back online emergency repair

Photo: NEK

Published

November 20, 2023

Country

Comments

comments icon

0

Share

Published:

November 20, 2023

Country:

Comments:

comments icon

0

Share

Parts of pipelines on both sides of the reactor vessel in the Krško nuclear plant were replaced as a precaution due to a leakage detected on the reducer section in early October. The facility was reconnected to the power network and its capacity utilization is being gradually increased.

The Krško nuclear power plant was resynchronized with the electricity grid after it was preventively shut down on October 6 due to a leak. Slovenia’s power system stability was put under an additional test with an outage of unit 6 in the Šoštanj coal-fired power plant last week because of a malfunction in the transportation of slag from the boiler. The other unit wasn’t affected.

Both facilities came back online on November 17. Combined, the nuclear and thermal power plant account for two thirds of the country’s domestic electricity output. It should also be noted that Slovenia covers 30% of its power consumption from imports.

Regular overhaul due in April

Krško was relaunched with a capacity utilization rate of 28%, which is being gradually increased, according to its operator NEK. It is a joint venture of Slovenian government-controlled utility GEN energija and Croatia’s Hrvatska Elektroprivreda (HEP Group).

Krško has 696 MW in capacity. It is scheduled for an overhaul in April. Slovenia is planning to build another nuclear power plant.

Westinghouse handles repair

As for the leakage, detected on October 4, the hole was within the primary cooling circuit, in the reducer section of the pipeline. It was on a high-pressure safety injection system, which is one of the emergency core cooling systems.

Westinghouse, the original designer and equipment supplier, repaired the malfunction, helped by domestic companies. Sections of pipelines on both sides of the reactor vessel were replaced until the check valves.

All 121 fuel elements were transferred to the spent fuel pool to enable the repair.

NEK said it is already contracting metallographic research and thermohydraulic and mechanical analyses to determine and analyze the cause of the failure. It plans to complete the examinations within one year.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

EVN Macedonia BESS 10 MW into operation at solar park

EVN Macedonia puts BESS of 10 MW into operation at its solar park

13 May 2026 - EVN Macedonia commissioned a battery energy storage system within its Probištip photovoltaic plant in North Macedonia

Energy companies confront dual mandate keeping supply secure while accelerating green transition BEF 2026

Energy companies in Western Balkans confront dual mandate – keeping supply secure while accelerating green transition

13 May 2026 - Companies in the region have challenges in energy security, decarbonization and digitalization, and the key is investing in production, the grid and batteries, according to the panel on power system transition at Belgrade Energy Forum 2026

serbia eu region bef 2026 ivan asanovic cges market coupling

Asanović: Montenegro expects European Commission to clear market coupling by end-June

12 May 2026 - Ivan Asanović, CEO of Montenegro's transmission system operator, participated in the panel on transmission grid development at BEF 2026

serbia eu region bef 2026 jelena matejic ems renewables grid connection

Matejić: Serbia’s grid to integrate 12 GW of renewables in next six years

12 May 2026 - Jelena Matejić, General Manager of Elektromreža Srbije, took part in a panel on transmission grids at Belgrade Energy Forum 2026