Electricity

Hungary, Slovenia connect electricity systems with Cirkovce-Pince link

Slovenia, Hungary connect power systems - transmission line Cirkovce-Pince finished

Photo: ELES

Published

July 4, 2022

Country

Comments

comments icon

0

Share

Published:

July 4, 2022

Country:

Comments:

comments icon

0

Share

The Cirkovce-Pince-Hévíz power transmission line, the first between Hungary and Slovenia, is now operational, national transmission system operators ELES and MAVIR have announced.

Power line Cirkovce-Pince-Hévíz is operating as testing and trial-run are underway, while the interconnection will be included in the cross-border capacity calculation process starting from July 6, 2022.

The cross-border project implemented by ELES envisages the construction of the 80.5 km long double circuit 400kV overhead line Cirkovce-Pince and the new 400 kV Cirkovce substation, both in Slovenia.

ELES, and MAVIR said that the planned physical connection between the Hungarian and the Slovenian electricity systems was established on the scheduled date of June 30.

The Cirkovce-Pince transmission line is the last phase Hungarian-Croatian-Slovenian 400 kV transmission grid connection

The transmission system operators ELES, MAVIR, and Croatia’s HOPS carried out preliminary tests and measurements of the newly built international connection, which will provide a more stable and reliable operation of the electricity system at the 400 kV voltage level and contribute to an even the stronger connection of these markets to common EU internal electricity market.

Slovenia, Hungary connect power systems - transmission line Cirkovce-Pince

The construction of the Cirkovce-Pince transmission line is the last phase of the Hungarian-Croatian-Slovenian 400 kV transmission grid connection project which implementation started in mid-1990s. The power line is connected to one circuit of the existing double circuit 400kV OHL Hévíz (Hungary) – Žerjavinec (Croatia).

The transmission line construction took place from August 2020 to June 2022

On the Hungarian side, a double-circuit tie-line between Hévíz and the Slovenian-Croatian-Hungarian border was completed before the turn of the millennium. The Slovenian system has now been connected to a 5-kilometer branch constructed earlier by Hungary.

The transmission line construction took place from August 2020 to June 2022 on the Slovenian side, when all the conditions were met for the transmission line to be energized, ELES said.

The Hévíz – Cirkovce – Pince 2×400 kV international transmission line project between Hungary and Slovenia is significant for EU energy policy purposes, which is why it was included in the list of the so-called Projects of Common Interest (PCI).

The project has received EU funding

The project overhead line 2×400 kV Cirkovce – Pince and the substation 400/110 kV Cirkovce has received EUR 48.2 million under Connecting Europe Facility (CEF). The overall investment was estimated at EUR 102.5 million.

ENTSO-E earlier aid that the project will establish two new cross-border lines – Heviz-Cirkovce and Cirkovce-Žerjavinec.

The project will allow Slovenia, Hungary, Italy and surrounding countries to access energy markets in the east, including import, and improve reliability and security of supply.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Romania risks power outages as import capacity is nearing its limits

Romania risks power outages as import capacity is nearing its limits

09 December 2024 - Imports account for over 35% of power consumption in Romania during daily peaks, but Minister of Energy Sebastian Burduja isn't pessimistic

montenegro tpp pljevlja sasa mujovic necp

Montenegro drafts NECP: TPP Pljevlja to be shut down by 2041

09 December 2024 - The Ministry of Energy of Montenegro submitted the draft NECP to the Energy Community Secretariat for a review

Bulgaria call standalone energy storage 4 3 times oversubscribed

Bulgaria’s call for standalone energy storage is 4.3 times oversubscribed

09 December 2024 - Developers in Bulgaria applied for 4.3 times more in grants for standalone energy storage than the budget. Funding is uncertain, though.

Bulgarian citizens demand referendum on wind farm construction on agricultural land

Bulgarian citizens demand referendum on wind farms on agricultural land

09 December 2024 - Citizens from four Bulgarian districts protested in Varna, calling for a referendum on constructing solar and wind farms on agricultural land