Renewables

Turkey starts building solar parks on former coal land

Turkey starts building solar parks on former coal land

Photo: Republic of Türkiye Ministry of Energy and Natural Resources

Published

September 23, 2025

Country

Comments

comments icon

0

Share

Published:

September 23, 2025

Country:

Comments:

comments icon

0

Share

After the first two units of 5 MW each, state-owned Turkish Coal Enterprises (TKI) is planning two solar power plants of 14 MW in combined peak capacity at sites of its previous mining operations.

Former coal mines and their tailings dumps, together with the ash disposal fields of thermal power plants, are among the most convenient areas for solar power plants, unlike fertile agricultural land. In Southeastern Europe, Greece is leading the way by transforming its coal land into industrial hubs with cutting-edge technologies, with the focus remaining on energy – mostly solar power plants. Their capacity is among the highest in the world.

Other countries in the region are advancing slowly in such decarbonization projects, with the exception of North Macedonia, or are still in the planning stage, but Turkey announced that it intends to speed up the construction of photovoltaic units on sites of former coal mining operations.

The Ministry of Energy and Natural Resources said the capacity would reach 24 MW next year

Turkish Coal Enterprises (TKI) is revitalizing the areas of depleted open pit mines also through afforestation, the Ministry of Energy and Natural Resources said. The company planted just over 12 million trees on 6,265 hectares last year.

With photovoltaic projects, such areas are contributing to the country’s economy again. The state-owned company’s Aegean region subsidiary ELI operates a self-consumption unit of 5 MW in Manisa. Another firm, ÇLI, based in Çanakkale, further to the north, has installed a 5 MW solar park.

The two facilities generate 18 GWh of electricity per year, supplying businesses, the update adds.

Preparations are underway for the construction of a 5 MW photovoltaic plant in the Tavşanlı district of Kütahya province in Turkey’s west. Another project is for 9 MW in the Afşin district in Kahramanmaraş, in the Mediterranean region in the country’s south. TKI plans to complete them next year.

The four solar parks will produce some 41 GWh per year, according to the ministry.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bih hydrogen project energoinvest epbih H2OIE cei

BiH starts working on national hydrogen strategy

13 February 2026 - The implementation of the CEI Support to Hydrogen Strategy Development and Know-How Transfer for BiH project began in Sarajevo

Romania one small reactor test before proceeding SMR project

Romania to build one small reactor to test before proceeding with six-unit SMR project

13 February 2026 - Nuclearelectrica voted to launch the investment in an SMR project of 462 MW. Reportedly, it would build and test one of the six units before continuing.

serbia electricity market rules ems nikola tosic balancing

Serbia’s new electricity market rules bring important changes

12 February 2026 - Nikola Tošić, Market Division Manager at Serbia's transmission system operator EMS, explains new electricity market rules

eu energy taxes prices Ursula von der Leyen European Industry Summit

Von der Leyen: EU working with member states to cut taxes and lower energy prices

12 February 2026 - The taxes that industry pays on power are 15 times higher than on gas, Ursula von der Leyen said at the Antwerp European Industry Summit