Fortis Energy preparing to build solar-battery hybrid power plant in Serbia

Fortis Energy solar battery hybrid power plant Serbia

Photo: City of Sremska Mitrovica

Published

September 21, 2025

Country

Comments

comments icon

0

Share

Published:

September 21, 2025

Country:

Comments:

comments icon

0

Share

Fortis Energy has obtained a construction permit for a solar park of 270 MW on the territory of the city of Sremska Mitrovica in Serbia, Mayor Branislav Nedimović said. The company plans to include a battery energy storage system (BESS) of 36 MWh.

Turkey-based Fortis Energy bought a solar power project in Serbia last year, which would have a 180 MW grid connection. At the time, the company announced that it also planned a battery energy storage system of 36 MWh. Chief Operational Officer Velimir Gavrilović said in May, at Belgrade Energy Forum (BEF 2025) that the projects Noćaj 1 and Noćaj 2 are nearing a ready-to-build status.

After his recent meeting with the representatives of Fortis Energy, Mayor of Sremska Mitrovica Branislav Nedimović said the company has obtained a construction permit for the solar park. The transmission permit is expected within three months, and the works are beginning in the spring, he revealed. Sremska Mitrovica is a city west of Belgrade.

The location is on private land just south of the river Sava, toward Drenovac village in the Mačva area, Nedimović asserted. He said the solar power plant’s capacity would be 270 MW.

Fortis Energy received a construction permit for a proposed solar park across the river from Sremska Mitrovica

In May, the company signed a contract for the connection of its planned solar park Erdevik in Šid, a municipality bordering Sremska Mitrovica. The plan is to install 110 MW in peak capacity, with a BESS system of 31.2 MWh.

The developer and engineering, procurement and construction (EPC) contractor is working on wind power projects Vranje, Gornjak and Juhor.

The company has five biogas facilities of 21 MW altogether, including its Dolovo system in Serbia.

Last year in North Macedonia, Fortis Energy commissioned a photovoltaic plant of 79.9 MW in peak capacity in Oslomej in North Macedonia. The grid capacity is 68.7 MW.

The company said in February that it contracted the construction of a BESS of 62 MW at the same location. It opted for lithium ion batteries of 104 MWh in total capacity.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

slovenia region evropa electricity prices mervar forecast

Mervar: Electricity prices 40% higher until end-2026

02 April 2026 - ELES CEO Aleksander Mervar prepared a brief analysis of electricity price trends in light of the war in the Middle East

First battery energy storage systems enter Greek electricity market

First battery energy storage systems enter Greek electricity market

02 April 2026 - The Hellenic Energy Exchange introduced Greece's first battery energy storage systems (BESS) into the day-ahead and intraday markets

bulgaria electricity prices subsidies energy crisis iran traycho traykov

Bulgaria plans scheme to subsidize electricity prices for businesses

01 April 2026 - On Bulgaria's power exchange, IBEX, the day-ahead price for April 2 reached EUR 136.6 per MWh, compared to EUR 67.5 per MWh on February 27

Siemens Energy to replace transformers at Romania's largest hydropower plant Iron Gate 1

Siemens Energy to replace transformers at Romania’s largest hydropower plant

01 April 2026 - Hidroelectrica picked Siemens Energy to supply seven transformers within the modernization of the Iron Gate 1 hydropower plant on the Danube