Necessary investments in Bosnia and Herzegovina’s electricity distribution grids by 2030 amount to BAM 1.4 billion (EUR 716 million), according to Zijad Bajramović, chairman of the Bosnia and Herzegovina committee of the International Council on Large Electric Systems (CIGRE).

The growing installation of power plants utilizing renewable energy sources is creating congestion in transmission and distribution networks, so the limited available capacity for their connection is an issue across the entire region, Zijad Bajramović told state news agency Fena. Nezavisne Novine republished the report.

An additional burden on the distribution network is expected from the electrification of transportation and increased electricity use for heating and cooling.

Energy storage is a solution for the problems emerging in the grid

Bajramović explained that new 110 kV substations are necessary, as is the completion of the ongoing transition to the 20 kV voltage level. Attention should also be paid to integrating prosumers, especially the households that both produce electricity, with solar panels on their roofs, and consume it.

He highlighted balancing as well as maintaining voltage conditions and supply quality as the main challenges from the rise in renewable electricity capacity on the grid. Energy storage is a solution for the issues.

Batteries can prevent renewables generation curtailments

Bajramović expects battery energy storage systems to play an increasingly significant role in relieving network congestion.

BESS, in his words, are a flexibility tool for absorbing excess generation locally, and temporarily easing the pressure on the transmission grid. They can prevent curtailments of power generation from variable renewable sources, he added.

Bajramović recalled that calculations have showed batteries of 225 MW / 450 MWh in total would be necessary to connect 1,500 MW of solar power capacity and 1,000 MW of wind power to the transmission network.

An increase in distribution network tariffs would provide funds for investment in strengthening and modernizing the distribution network, in his view.

Batteries are being installed at a rapid rate around the world as well as in the region. Not only private companies, but also state-owned utilities such as Romania’s Hidroelectrica and Montenegro’s Elektroprivreda Crne Gore (EPCG) are investing in such projects.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

nova bess romania battery

Romania’s biggest battery system put into operation

13 December 2025 - Nova Power & Gas has commissioned a battery energy storage system with an operating power of 200 MW and a capacity of 400 MWh

north macedonia power line dalekovod kodar elnos mepso croatia serbia bih

Firms from Croatia, BiH, Serbia to build power line in North Macedonia

12 December 2025 - The contracted works include the construction of a 400 kV power line from the 400/110 kV Bitola 2 substation to the border with Albania 

slovenia climate vulnerability risks energy assessment

Slovenia draws up first climate vulnerability, risks assessment for energy sector

12 December 2025 - The assessment was prepared by the Ministry of the Environment, Climate and Energy, in cooperation with the Jožef Stefan Institute

Turkey awards 1 15 GW wind power auctions all at EUR 35 per MWh

Turkey awards 1.15 GW in wind power auctions – all at just EUR 35 per MWh

12 December 2025 - The six winners from the latest round of wind power auctions under the YEKA mechanism in Turkey have EUR 35 per MWh guaranteed