Investors in standalone batteries in Greece request extension as deadline looms

Investors in standalone batteries request extension as deadline looms in Greece

Photo: DC Studio on freepik.com

Published

August 22, 2025

Country

Comments

comments icon

0

Share

Published:

August 22, 2025

Country:

Comments:

comments icon

0

Share

September 30 marks a crucial deadline for standalone battery projects selected through Greece’s first two auctions.

Investors in battery projects of about 700 MW in total are rushing to submit their so-called declarations of readiness to the Independent Power Transmission Operator (IPTO or ADMIE) by the end of September. After that point, the projects must become operational by the end of the year.

Investors claim that a lengthy licensing process, combined with a one year equipment procurement span, means many will be unable to reach the finish line in time. Licensing delays also caused problems with financing.

If a project breaches the deadlines, it will be subject to the loss of the letter of guarantee, resulting in losses that can even reach several million euros, depending on the capacity of the battery.

The deadline for commissioning for projects selected through the third auction, which amount to 200 MW, is April 30.

Market warns of insufficient time for batteries

The Hellenic Association of Energy Storage Systems (HAESS) has asked for more time and a new final declarations deadline, end-July 2026, for the projects selected through all three auctions. It added that the investors of the first two rounds only managed to acquire connection terms by mid-year.

The deadlines are binding to secure funding from the European Union’s Recovery and Resilience Facility (RRF), the organization explained. It means that if the timeframe is breached, selected projects will not receive support.

So far there has been no official statement about the possibility of extending the deadlines. Therefore, it remains to be seen whether the Ministry of Environment and Energy will maintain a strict stance, as Greece urgently needs storage to address ever higher curtailments.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia hemofarm rooftop solar plant vrsac

Hemofarm commissions one of largest rooftop solar plants in Serbia

27 February 2026 - The largest rooftop solar plant in Serbia is on the buildings of polymer products maker Peštan

bih republic of srpska loans garanties power plants distribution grid petar djokic

Republic of Srpska plans EUR 204 million in loans for power plants, grid

27 February 2026 - The Republic of Srpska is ready to issue guarantees for BAM 400 million (EUR 204.5 million) for coal power plants and the distribution grid

Romania earmarks subsidies for standalone BESS projects

Romania earmarks subsidies for standalone BESS projects

27 February 2026 - Romania expects ten projects for standalone battery energy storage systems (BESS) to benefit from its new EUR 150 million support scheme

vlasina hydropower plants cascade eps modernization rehabilitation

Serbia officially launches modernization of Vlasina hydropower plants

27 February 2026 - The rehabilitation project will increase the installed capacity and extend the operating life of the Vlasina hydropower cascade