Shikun and Binui Energy finishing 71 MW solar park in Romania

Shikun and Binui Energy finishing 71 MW solar park Romania

Photo: Jcomp on Freepik

Published

November 26, 2024

Country

Comments

comments icon

0

Share

Published:

November 26, 2024

Country:

Comments:

comments icon

0

Share

The Satu Mare photovoltaic plant will likely start production in the first quarter, Shikun and Binui Energy said. The company energized a transformer at the site, in northwest Romania.

After years of accumulation of projects in Romania, the solar power boom is in full swing. Companies are obtaining loans, beginning construction and commissioning utility-scale photovoltaic facilities every few days. Israel-based Shikun and Binui Energy announced that it has energized a transformer within its Satu Mare project.

The site spanning 85 hectares is in the country’s northeast. The 71 MW project is the company’s first big investment in Europe.

Commissioning possible ahead of schedule

The Satu Mare solar park, located in the county of the same name, will start delivering electricity as early as next quarter, Shikun and Binui Energy said. Earlier it planned to commission it in the second quarter of 2025.

The contractor is CJR Renewables. Late last year it signed the turnkey deal including design, civil, mechanical and electrical engineering, equipment procurement and construction.

Shikun and Binui Energy secured a EUR 40.5 million loan in March from Raiffeisen Bank International and its Romanian subsidiary.

The company said it has a 1.5 GW pipeline of solar and wind power projects in the country.

Of note, Electrica is preparing to launch construction of Satu Mare 2 and 3 in the same area.

Shikun and Binui Energy also invests big in wind power in Romania

Shikun and Binui Energy earlier secured a EUR 49 million loan for Șimleu Silvaniei. The location for the 101 MW photovoltaic endeavor is in the nearby Salaj county.

It also got a transmission network connection approval for its proposed Gold-Wind wind farm of 376 MW near Constanța. Target completion date is by the end of 2028.

According to news reports from a year ago, the company also had wind and solar power projects in Iași county.

It specializes in the development, construction, operation and maintenance of renewable energy facilities including solar thermal systems, pumped and battery storage and agrivoltaics. Its parent company Shikun and Binui operates in the infrastructure and real estate sectors.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bih hydrogen project energoinvest epbih H2OIE cei

BiH starts working on national hydrogen strategy

13 February 2026 - The implementation of the CEI Support to Hydrogen Strategy Development and Know-How Transfer for BiH project began in Sarajevo

Romania one small reactor test before proceeding SMR project

Romania to build one small reactor to test before proceeding with six-unit SMR project

13 February 2026 - Nuclearelectrica voted to launch the investment in an SMR project of 462 MW. Reportedly, it would build and test one of the six units before continuing.

serbia electricity market rules ems nikola tosic balancing

Serbia’s new electricity market rules bring important changes

12 February 2026 - Nikola Tošić, Market Division Manager at Serbia's transmission system operator EMS, explains new electricity market rules

eu energy taxes prices Ursula von der Leyen European Industry Summit

Von der Leyen: EU working with member states to cut taxes and lower energy prices

12 February 2026 - The taxes that industry pays on power are 15 times higher than on gas, Ursula von der Leyen said at the Antwerp European Industry Summit