Montenegro to delay temporary shutdown of TPP Pljevlja for 2026

Montenegro to delay shutdown of TPP Pljevlja for 2026 EPCG miro vracar

Miro Vračar (photo: Printscreen/RTNK)

Published

September 2, 2024

Country

Comments

comments icon

0

Share

Published:

September 2, 2024

Country:

Comments:

comments icon

0

Share

The pause in the operation of the Pljevlja coal power plant in Montenegro, planned for 2025 within its so-called ecological reconstruction, could be postponed to 2026, according to Miro Vračar, assistant to executive director of state-owned power utility Elektroprivreda Crne Gore (EPCG). He also said the drought weakened hydropower production and revealed that the company would build wind farm Gvozd 2.

The delay in the preparation of project documentation and the procurement of equipment will probably postpone the ecological reconstruction of coal-fired power plant Pljevlja for 2026, RTNK reported.

EPCG will see with the contractor whether it is prepared to proceed to the standstill next year, Miro Vračar said. “Our assessment is that it isn’t,” he stressed and added that the plan for a suspension in the operation of the facility in 2025 isn’t final.

In April 2022 EPCG kicked off the ecological reconstruction of TPP Pljevlja to bring its emissions in line with the European Union’s standards and extend its lifespan. It would also fulfill its obligations within the Energy Community.

Hydropower production is below plan

The most important part of the reconstruction is halting the operation of the power plant for six to eight months. It would significantly lower the domestic production of electricity because Pljevlja, which has 250 MW, accounts for almost 40%.

Early this year, Minister of Energy and Mining Saša Mujović noted that the standstill would force Montenegro to import large amounts of electricity, valued at EUR 160 million.

Vračar also said that due to bad hydrology, production in hydropower plant Perućica in the first eight months of the year was 18% lower than planned, compared to the underperformance of 7% at EPCG’s other major hydroelectric facility, Piva.

Stronger wind turbines for the Gvozd project

This summer Montenegro imported electricity. Vračar stressed that the company was purchasing it when it was cheapest, around noon, and selling in the evening, when it was seven to 10 times more expensive. EPCG hopes that in the last quarter hydrology will be better, which would improve the energy and financial balances, he added.

Regarding the Gvozd wind farm project, Vračar said the construction, planned to start in the second quarter, was postponed because of a change in wind turbine capacity.

Instead of 12, EPCG will install eight stronger turbines, opening the way for the Gvozd 2 project because then four fields are left for windmills, which will have 25 MW combined, Vračar said.

The total capacity of the wind farms will be 80 MW to 85 MW, in his words.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia drafts just transition action plan public debate

Serbia drafts just transition action plan

30 May 2025 - The Ministry of Mining and Energy has published a draft just transition action plan and launched a public debate

Regional Power Sector Exchange Western Balkans disitribution system operator dso grids ohrid giz

Third Regional Power Sector Exchange in Ohrid: Power grids at core of energy transition

30 May 2025 - The third Regional Power Sector Exchange of the Western Balkans gathered over 80 energy professionals from the Western Balkans

two solar power plants egesa enerji vojvodina

Turkish Egesa Enerji to build two solar power plants in Serbia’s Vojvodina province

30 May 2025 - Turkish company Egesa Enerji has launched a project to build two solar power plants in Vojvodina, with a total nominal capacity of 8.6 MW

Green for Growth Fund partnership Swedish International Development Cooperation Agency Sida

Green for Growth Fund launches partnership with Swedish International Development Cooperation Agency

30 May 2025 - GGF and the Swedish International Development Cooperation Agency are expanding green lending in the Western Balkans and the EU's Eastern Neighborhood