EDF scraps project Nuward to turn to simpler small modular reactor design

EDF scraps project Nuward turn to simpler small modular reactor design

Photo: EDF

Published

July 3, 2024

Country

Comments

comments icon

0

Share

Published:

July 3, 2024

Country:

Comments:

comments icon

0

Share

French state-owned nuclear power giant EDF gave up on its original vision for an innovative small modular reactor, turning instead to proven technologies. After several years of development, it intends to thoroughly revise the Nuward design.

The only European developer of third-generation small modular reactors (SMRs) is about to formally scrap its innovative solutions after consulting regulators and potential clients. France’s state-controlled energy utility EDF acknowledged that it would turn to a more classic design. The Nuward SMR concept is seemingly too complex and expensive.

Among other in-house systems under development was an integrated boiler. Nuward was advertised as a nuclear power plant with two pressurized water reactors of 170 MW each. The thermal energy capacity would be 540 MW apiece. The SMR’s targeted lifespan was 60 years. It would take 40 months to build.

Nuward was supposed to include desalination, heat production

EDF earlier said it sees Nuward as a complementary solution to renewables. It would replace aging coal-fired power plants in the range of  300 MW to 400 MW. The company’s SMR systems were intended to supply remote municipalities and energy-intensive industrial sites where the grid capacity is limited.

The project, launched in 2019, included seawater desalination and heat production. France is making efforts to renew and expand its nuclear fleet and promote its technology throughout Europe and beyond.

EDF still aspires to get gen-3 SMR out into market

The partners in the Nuward endeavor were small reactor manufacturer TechnicAtome, EDF’s joint venture Framatome (with Mitsubishi Heavy Industries), the French Alternative Energies and Atomic Energy Commission (CEA), Belgium-based Tractebel and naval defense and energy developer and manufacturer Naval Group.

Nuward has reached the detailed design stage before the surprise turnaround. EDF said it would continue work on the market launch of a generation 3 small modular reactor.

It reached the decision following a review by six safety authorities, the domestic media reported, and after it received feedback from companies including Vattenfall, ČEZ and Fortum.

Only a handful of mostly pilot SMR projects are operational or under construction in the world.

Of note, Serbia and Montenegro recently signed memorandums of understanding with EDF on cooperation in the energy sector.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia to prepare by 2032 for nuclear plant construction Russia possible partner

Serbia to prepare by 2032 for nuclear plant construction – Russia possible partner

23 February 2026 - Serbia is building its nuclear program with EDF for a 2032 launch, but remains open to other partners like Rosatom

Aurora Romania Bulgaria top 10 European battery markets

Aurora: Romania, Bulgaria among top 10 European battery markets

23 February 2026 - Romania and Bulgaria are among the frontrunners in Aurora Energy Research's new European Battery Markets Attractiveness Report

montenegro zorana sekulic interview hydrogen program action plan ministry of energy

Sekulić: Montenegro is preparing for a hydrogen energy era

20 February 2026 - Zorana Sekulić, Director of the Directorate for Oil and Gas at the Ministry of Energy and Mining, is finishing doctoral studies in hydrogen

coal mining

Coal miners’ woes threaten electricity production across region

20 February 2026 - Miners at Romania’s coal complex CE Oltenia have staged protests, including hunger strikes, over plans to scrap meal vouchers and cut wages