Serbia’s EPS to start trial of flue gas desulphurization facility at TPP TENT A by April

eps tent flue gas desulphurization facility

Photo: EPS

Published

January 19, 2024

Country

Comments

0

Share

Published:

January 19, 2024

Country:

Comments:

0

Share

The construction of a flue gas desulphurization facility at coal-fired power plant Nikola Tesla A is in its final phase and trial work should begin by April, Minister of Mining and Energy of Serbia Dubravka Đedović Handanović said.

The flue gas desulphurization facility at thermal power plant Nikola Tesla A (TENT A) also started to produce gypsum, a byproduct of the process.

It is one of the most important environmental projects in Serbia, Đedović Handanović said.

The minister noted it would bring cleaner air for the citizens of nearby Obrenovac and its surroundings and added it would cut sulphur dioxide emissions by ten times.

EPS can play a significant role in the circular economy

The investment will also extend the lifespan of TENT A and make it comply with European Union standards on emission limit values, Đedović Handanović said.

The flue gas desulfurization unit in TENT A, operated by state-owned power utility Elektroprivreda Srbije (EPS), will serve units A3 to A6.

She pointed out that the facility enables gypsum to be produced from waste as a byproduct, to be used in the construction industry. It demonstrates that EPS can play a significant role in the circular economy, the minister stressed.

The desulfurization project in TENT A is implemented with financial support from the Japan International Cooperation Agency (JICA), and the contractor is the Japanese company Mitsubishi. Of note, a similar unit is under construction in TENT B, where sulphur dioxide emissions are envisaged to be reduced by twenty times.

EPS: Emissions in line with EU regulations

By purifying the flue gases at four units of 350 MW each, the sulphur oxide emissions will be reduced to below 200 milligrams per cubic meter, and particulate matter (PM) to under 20 milligrams per cubic meter, in line with EU standards and domestic regulations, said Srđan Josipović, director of energy production at the TENT complex.

The emissions of sulphur oxides in TENT B will be below 130 milligrams per cubic meter.

The company also said that the flue gas desulphurization facility in TENT A is EPS’s most important environmental project. It is worth almost EUR 205 million.

According to project manager Ljiljana Velimirović, the annual production of gypsum is expected to reach 600,000 tons.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

CBAM ante portas – the ball is in Serbia’s court to facilitate conditions for its companies

CBAM ante portas – the ball is in Serbia’s court to facilitate conditions for its companies

12 May 2024 - Industrial players in Serbia have all the knowhow for minimizing emissions and participating in the country's environmental renewal, according to Lafarge Serbia's CEO Dimitrije Knjeginjić

State owned DEM operate Slovenia fourth wind turbine

State-owned DEM to operate Slovenia’s fourth wind turbine

10 May 2024 - Dravske elektrarne Maribor hired Ljubljana-based Hmezad TMT for the construction of a single-turbine wind power plant in southern Slovenia

eu solar rooftop standard directive epbd

EU Solar Rooftop Standard could initiate installation of 150 GW to 200 GW of rooftop PV

09 May 2024 - The standard is part of the EU Energy Performance of Buildings Directive, which entered into force yesterday

Chinese company Hunan Rich solar panel factory Serbia

Chinese company Hunan Rich to build solar panel factory in Serbia

09 May 2024 - Chinese company Hunan Rich Photovoltaic Science and Technology signed a deal for a solar power panel factory and photovoltaic plant in Serbia