North Macedonia to cancel Čebren deal with PPC, Archirodon

North Macedonia cancel Cebren PPC Archirodon

Photo: Maniacvector

Published

January 3, 2024

Country

Comments

comments icon

0

Share

Published:

January 3, 2024

Country:

Comments:

comments icon

0

Share

Minister of Environment and Spatial Planning Kaja Šukova said the Government of North Macedonia would annul the tender in which Greek companies PPC and Archirodon were selected for the Čebren pumped storage hydropower project.

Two years after the start of the 14th attempt to find a partner for the construction and operation of one of the largest energy systems in North Macedonia, it’s back to the drawing board again. Minister of Environment and Spatial Planning Kaja Šukova said she would propose the cancellation of the deal with Greece-based Public Power Corp. (PPC) and Archirodon. The consortium was selected in September.

The idea for the Čebren pumped storage hydropower plant dates back to the 1960s. The energy storage project for 333 MW to 458 MW in capacity is valued at EUR 1 billion. Annual output would be between 1 GW and 1.2 GW.

The two companies were supposed to establish a public-private partnership with state-owned electricity producer and supplier Elektrani na Severna Makedonija (ESM).

Archirodon sought a change in the terms of the proposed deal but the government wouldn’t change its original offer, Minister Kaja Šukova claimed

Archirodon obviously couldn’t obtain bank loans under the conditions set in the tender, Šukova said. She pointed out that its bank guarantee expired at the end of December, so that the arrangement is off. The company sought a change in the terms of the proposed deal but the government stood by the initial conditions, the minister claimed.

Energy experts and decision makers in the sector should now discuss whether to launch another public call or if North Macedonia should install the pumped storage hydropower plant on its own, Šukova added.

Studies conducted before the tender showed there would be no significant impacts on the environment, in her words. The failed public calls began two decades ago and the previous one was published in 2016.

According to indications from state officials over the past few months, the foreign partners were supposed to obtain a water concession before signing the contract, and it became a sticking point.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

north macedonia esm ivan stojanovski investments solar wind gas batteries

North Macedonia’s ESM needs investments of EUR 3 billion to replace coal power

03 November 2025 - Balkan Green Energy News spoke with ESM's CFO Ivan Stojanovski on the sidelines of the International Forum on Energy for Sustainable Development

Cypriot firm several solar parks with batteries SAOLA

Cypriot firm preparing to build several solar parks with batteries

03 November 2025 - Larnaca-based SAOLA plans to build a group of small hybrid power plants consisting of photovoltaic units and battery energy storage systems

R.Power first solar parks Romania construction phase

R.Power completing its first solar parks in Romania while more assets enter construction phase

03 November 2025 - Poland-based R.Power began work on its Lazuri photovoltaic plant of 55 MW in peak capacity in Satu Mare county in northwestern Romania

north macedonia forum skopje declaration sustainable energy undep sanja bozinovska grigorian liguti

Skopje Declaration signed as International Forum on Energy for Sustainable Development wraps up

31 October 2025 - The three-day International Forum on Energy for Sustainable Development (IFESD-14) brought together over 500 participants from 70 countries