The construction of the first section of a 1,200-kilometer national hydrogen network began near Rotterdam. Officials said the Netherlands would be the first country in Europe with such infrastructure.

Nederlandse Gasunie, the Dutch gas infrastructure and transmission operator, marked the beginning of the installation of a 30-kilometer hydrogen pipeline. It is the first part of a planned national network of 1,200 kilometers, valued at EUR 1.5 billion.

The first section, worth EUR 100 million, will run from the new port and industrial park Tweede Maasvlakte (Maasvlakte 2) near Rotterdam to Shell’s gas refinery in Pernis. The European Union is rolling out hefty subsidies to stimulate both the production and demand for low-carbon hydrogen, also known as clean hydrogen. The industry is still in a very early phase and such technologies have a long way to become competitive against hydrogen produced from fossil gas.

The idea behind the project is to connect industrial hubs within the Netherlands as well as with Germany and Belgium. The network is envisaged with storage facilities including a salt cavern in the country’s north.

Hydrogen infrastructure opens way for renewable energy investments

Gasunie is conducting the project through its subsidiary HyNetwork Services, which selected Visser en Smit Hanab as the contractor for the current phase. The company said the hydrogen network, set to become the first in Europe, would enable the establishment of a major renewable energy hub in the country.

Electricity from wind parks and solar farms is used in electrolyzers to produce green hydrogen by splitting water molecules. If the facility is powered by nuclear energy, the product is called pink hydrogen. A low-carbon version – blue hydrogen – can also be produced directly from fossil gas, but only if carbon dioxide emitted during the process is captured and permanently stored.

Repurposing existing gas lines is 75% cheaper than making new ones

The first segment of the new grid is scheduled to come online in 2025. Gasunie pointed out that 85% of the system would be made from repurposed natural gas pipelines. The solution is 75% cheaper than making new infrastructure, according to its calculations.

The EU is developing its European Hydrogen Backbone initiative for 28,000 kilometers of hydrogen lines to be installed by the end of the decade. The ambition is to almost double the network in the following ten years, to 53,000 kilometers.

As for other developments in the sector, German transmission system operators OGE (Open Gas Europe) and Nowega launched works two weeks ago on converting a 46-kilometer pipeline in Lower Saxony and North Rhine-Westphalia from fossil gas to hydrogen. The project is expected to be finished in 2025 as well. In addition, Nowega is about to start the conversion of an adjacent line.

Comments (1)
Inderjeet Singh / November 3, 2024

Overall article was very informative

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

world energy crisis war renewables boom Simon Stiell un

Energy crisis fueled by Iran war makes economic logic of renewables impossible to ignore

04 May 2026 - The energy crisis fueled by the Iran war has made the economic logic of renewables impossible to ignore, according to Simon Stiell

Batteries enable Bulgaria import cheap electricity domestic production exceeds demand

Batteries enable Bulgaria to import cheap electricity even when domestic production exceeds demand

04 May 2026 - Bulgaria's abundant energy storage enables importing electricity at low, zero or negative prices even when domestic production exceeds demand

Zatriq wind farm in Kosovo to be completed in July

Zatriq wind farm in Kosovo* to be completed in July

04 May 2026 - Turkey-based Çalik Renewables and domestic company Eurokos are building a 72 MW wind power plant in Kosovo*. They expect to finish it in July.

tokyo offshore wind farm floating 1 GW

Tokyo plans world’s biggest floating offshore wind farm of 1 GW

04 May 2026 - The authorities of Japan’s capital, Tokyo, plan to develop a floating offshore wind farm with a nameplate capacity of 1 GW