Maja Turković: Battery installation requirement to clear large number of requests for grid connection

BEF 2023 Maja Turkovic batteries grid connection

Maja Turković

Published

May 20, 2023

Country

,

Comments

0

Share

Published:

May 20, 2023

Country:

,

Comments:

0

Share

The new battery installation requirement for developers seeking grid connection permits will increase the cost of projects and automatically clear a large number of requests for grid connection, Maja Turković, Executive Vice President, CWP Europe, said at the Belgrade Energy Forum 2023 (BEF 2023), organised by Balkan Green Energy News.

Changes to the law on renewables, which introduced the battery installation requirement, was one of the main topics of the panel Major challenges for an increased share of renewable energy sources in the SEE region.

Maja Turković said that piled-up applications for grid connection in Serbia and across the region had brought projects to a standstill. The state has failed to protect its vital resource, the grid, in time, she added.

There are only 500 MW of batteries integrated into renewable energy plants across Europe

Many unknowns exist regarding the requirement to install batteries, and investors are still waiting to see the by-laws. However, if the idea were to unlock investments, this requirement would not help, according to Turković.

She said that battery installation would increase the cost of projects by 20-30%.

Participants in the panel noted that in the United States, 45% of all solar projects under development include a battery, compared to just 10% of wind projects, adding that this is because batteries are more compatible with solar.

Also, only 500 MW of batteries are integrated into renewable energy plants across Europe, with 40 GW of such power plants installed last year alone. Of the total of 500 MW of batteries, 270 MW is in Britain, which has a developed market for system services.

Turković: investors in wind or solar will have to finance batteries from their own capital

Revenue streams for batteries, according to her, are capacity markets and arbitration, as well as for the ancillary services. However, these revenues cannot be monetized to get financing from banks.

This means that investors in wind or solar will have to finance batteries from their own capital, which will quickly remove the bottleneck created by grid connection applications in Serbia, Turković concluded.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

western-balkan-power-utilties-decarbonization-plans

Decarbonizing Western Balkan power utilities: ambitious but flexible plans, with focus on investments and new technologies

17 May 2024 - Power utilities in the Western Balkans have ambitious goals for 2050, but are flexible in mapping the path because the development of technologies is unpredictable

Banks Serbia receiving lot requests grid connection guarantees Belgrade Energy Forum

Banks in Serbia receiving lot of requests for grid connection guarantees

17 May 2024 - Banks in Serbia are receiving numerous requests for guarantees for renewables requiring grid connection and most investors have firm collateral instruments, according to speakers at Belgrade Energy Forum

statkraft neoen croatia Arnaud Bellange Christophe Desplats-Redier

Statkraft acquires Neoen’s project portfolio in Croatia

17 May 2024 - According to Arnaud Bellanger, Country Manager for Croatia and France at Statkraft, the takeover deal covers about ten projects

Turkey adds 1 3 GW solar power capacity April alone

Turkey adds 1.3 GW in solar power capacity in April alone

17 May 2024 - Photovoltaic capacity in Turkey reached 13.9 GW by the end of last month or a stunning 1.3 GW more than on March 31