Bajazit Jašarević, chief executive of Elektroprivreda Bosne i Hercegovine dd (Electric Utility of Bosnia and Herzegovina – EPBiH), and Senad Salkić, chief capital investment officer of the utility, signed a contract on connecting wind park Podveležje to 110 kV transmission network with Matan Zarić, head of Transco (Elektroprenos-Elektroprijenos BiH ad), and Cvjetko Žepinić, its director for system operation and maintenance.

EPBiH said the value of contracted works and services is BAM 2.7 million (EUR 1.38 million). It includes the construction of a power transmission line including route selection, preparation and revision of the main project for the construction, obtaining necessary approvals, licenses and permits, resolving property issues, procurement and installation of materials and equipment, connecting substation Podveležje into the optical cable system, technical inspection and acceptance of works, obtaining use permit and commissioning of the highline in operation, the statement adds.

Connecting the power plant to the network will be based on the entrance-exit principle. The unit will be linked to a 110 kV transmission line from Jablanica hydropower facility to Mostar 2 substation, and for that it is necessary to build a 110 kV double-circuit highline at a distance of about 2.5 kilometres, documentation shows.

The deadline for the works is the end of May 2018, the state-owned utility said.

Related Articles

All set for construction of Široka draga wind park of 125.4 MW in BiH

All set for construction of Široka draga wind park of 125.4 MW in BiH

13 August 2024 - Local firm Imres Smart Greenergy signed the deal with the selected contractor on its Široka draga wind power project

montenegro lng terminal iap pipeline natural gas sahmanovic

IAP pipeline, LNG terminal are strategic projects for Montenegro – minister

12 August 2024 - The construction of an LNG terminal and the Ionian Adriatic Pipeline are strategic projects for the new Ministry of Mining, Oil and Gas

eps profit 2024 assembly report

Serbia’s EPS posts EUR 280.3 million profit for first half of 2024

12 August 2024 - Elektroprivreda Srbije has said that its net earnings were RSD 9.4 billion (EUR 80.3 million) higher than planned

Turkey promoting alternative Greece Cyprus power cable

Turkey promoting its alternative to Greece-Cyprus power cable

12 August 2024 - Last month Turkish warships chased away a vessel scanning the route for the Greece-Cyprus section of the Great Sea Interconnector